Hello Clairiana,

I think you should definitely get a non-binding offer. Preferably from the general contractor of your friends. You should not mention the currently stated budget for the time being. You can set the 500,000 of your friends as a guideline. You can always increase it later.

The construction costs per sqm naturally depend on the level of equipment. For example, you can choose tiles for 30 euros but also for 150 euros. Depending on individual wishes, it may also be that you end up below 2,000 per sqm in price.

Including the utility room, we will have 172 sqm. We are building with geothermal energy and a decentralized ventilation system with heat recovery. Including the costs for a 10 m³ cistern, connection costs, a small budget for the garden, as well as the material for self-performed work (laying laminate and painting), our plan is just under 300,000 + land. The electrical work might still increase the price. Thus, our price per sqm is about 1,750 euros (but including the additional services, which are often not included).
 

nordanney

2014-06-18 00:27:07
  • #2
I have already posted that the budget is more than sufficient with proper awarding. We end up with a final cost for the house construction of under 1,600 EUR per sqm of living space (with 250 sqm living space or 300 sqm footprint - no basement). This includes all construction costs, additional costs, incidental construction costs, outdoor facilities, architect, etc., only the land is missing. Very high-quality equipment with clinker brick, geothermal energy, central controlled residential ventilation/heat recovery, approx. "Kfw 60" colored windows, all shutters electric, partly home automation, light switches + sockets + LAN to no end, approx. 200 sqm oak floorboards, three bathrooms, built-in spotlights, almost exclusively floor-to-ceiling windows including skylights (reaching up to the knee wall), see-through fireplace as room divider, solid wood interior doors flush closing, garden fountain + garden house, wooden terrace approx. 70 sqm etc. The decisive factor was simply the size of the house, which brings you cost advantages. In my opinion, you can approach the house construction completely relaxed.
 

Elchitekt

2014-06-18 08:35:57
  • #3
I'll just jump in briefly. I must admit, in traditional single-family home construction (and I deal with builders daily), I have rarely read such a professional approach in advance. Certainly, many costs are still estimates, square meter figures need to be verified, and individual items checked. But all in all, you have put a lot of good thought into it and covered all the ins and outs well. The fact that you mentally approach many costs on the higher side helps later in being able to keep the budget. I live (and work) in the South Lower Saxony area, so I have a direct construction cost comparison and can assure you that you should be able to manage with the planned budget (provided no gold-plated faucets are to be installed). You separately list architect fees, which is important and correct if you plan to work with an independent architect and possibly build with them. And there are good ones with whom such a project can be well implemented. However, an architect will not offer fixed prices as a construction company does, so the variable in costs here will be greater than with a construction company. And even with construction companies, there are firms that work with architects on free designs – then the additional architect costs do not apply, at most planning fees may be involved, but these usually have to be borne. Or you mix the tasks, find a good planner for preliminary and design drafts, and have the costs calculated by a construction company. Then your costs are manageable (because the architect or planner does not have to accompany the entire construction project) and you are still free in planning (only it should be said that construction companies with their own planners cannot always implement fully submitted plans one to one because each company has its own standards). Have fun building! And from my point of view, your planned budget is sufficient :-)
 

Clairiana

2014-06-18 10:18:23
  • #4
Hello f-pNo, nordanney and elchitekt, thanks for the constructive answers. Nordanney, do you have a construction blog? At the latest with the oak floorboards (I love oak floorboards) a "I want that too" screamed through my ear. :) Unfortunately, I can only respond briefly because we are leaving for a short vacation this morning. Thanks for the information for now, I will get in touch again on Monday. :)
 

Elchitekt

2014-06-18 10:30:46
  • #5
Have fun on vacation, good rest, and creative thoughts!
 

Bauexperte

2014-06-18 11:26:53
  • #6
Hello,

to you too: the language on the internet is the informal "you" ... makes it simpler ;-)


First of all, it crucially depends on the planning of the plot; 220 sqm/living area can be too little with poor design, but with clever planning 180 sqm/living area can be a bullseye ;)

Based on the above information, I would estimate as follows (if completely awarded to a main contractor/general contractor); thus including architect services:

Land: approx. €150,000
City villa, KfW-70 on slab: €330,000
Additional construction costs: €35,000-40,000
Painting works in award (textured wallpaper): €15,500
Floor coverings in award (material value tiles €30.00): €18,000
Outdoor facilities in award and medium value: €16,000
Double garage as prefabricated garage 6.00 x 6.00 m: €12,000
Extras, such as remote control roller shutters for 20 windows: €6,900.00
Reserves for further extras: €10,000
Kitchen: approx. €15,000

Results in an estimated volume of €613,400 plus further special requests, such as partial brick cladding etc.

Rhenish regards
 

Similar topics
26.12.2012Prefabricated house / solid house, which construction companies?16
02.08.2013Construction cost estimate for our dream house12
16.10.2013Construction costs: Do lenders have to provide proof of construction costs without investments?10
09.04.2014Questions/neglected plot/meadow, determining construction measures44
18.01.2016Geothermal energy: pros and cons?!41
11.02.2015Cost planning for a single-family house including land, additional costs, architect32
31.03.2015Property / Financing amount / Insurance? Experiences10
05.04.2015Property reserved. Financing is pending52
14.12.2017Property acquisition tax notice for land same contract document21
13.03.2018Turnkey Construction Land and Prices79
24.09.2015Divide and build on an indivisible plot of land18
21.03.2016Own work - floor coverings, painting, tiling, what else?40
28.05.2018Construction costs mini-bungalow (approx. 50m²)54
07.08.2017Construction costs approx. 400K - Is financing construction feasible this way?11
19.08.2017Construction costs in BW for a single-family house with a 200m2 basement and double garage38
22.08.2017Connection between financial intermediary and construction company14
22.04.2018New single-family house - realistic estimate of construction costs? Experiences?59
05.10.2018Buy land first, then build - experiences / tips?26
02.12.2020Surcharge for property "large but"32

Oben