Hello Greg,
Originally, our house was planned with about 350k EUR, which gradually increased from meeting to meeting and has now made another jump of 90k EUR, so according to the new estimate we are at 485k EUR.
Raw data:
Living area: 188m²
Number of floors: 1 plus knee wall. Roof area = 210m²
Top view attached.
Plot:
Already available and registered in the land register
Subtotal house construction net
351,527.00
Subtotal house construction gross 418,317.13
Architect
Subtotal architect gross 48,000.00
TOTAL Gross 485,000
.... still, I would like to hear your opinion on the costs.
I am always grateful when architects reasonably calculate the possible costs. But the above seems to me far beyond the target, especially since the sanitary equipment (what does that mean in this context, high quality?) as well as development costs are not yet included in the price.
Provider timber frame is not the same as provider timber frame, therefore I assume here good standard, i.e. higher construction costs than usual in the north. Accordingly, the building project might incur the following peak costs in my opinion:
Single-family house with 188 sqm and KfW 70: TEUR 340 (incl. renewable energies + architecture costs)
Additional building costs: TEUR 40 (notary costs are included here; negligible since you own the land)
Painting work & floor coverings in EL: TEUR 20
Outdoor facilities in EL: TEUR 10 (only the essentials — can become a barrel without a bottom; but usually developed over years)
Reserve for extras: TEUR 10
All in: TEUR 420
Final remark: the above cost breakdown of your architect cannot be assessed as is, because you have compressed too much.
Rhenish greetings