Passive house requirements of the city are not included in the development plan

  • Erstellt am 2025-07-17 07:27:45

Rübe1

2025-07-17 10:14:51
  • #1
au contraire

If you buy from the city of Ulm, please take a look at the sample purchase contract. There is a contractual agreement, especially § 2 no. 5.

If the city now requires you to build a PH when awarding because you cannot be connected, then you have a problem. In this respect, either you build PH or you do not get the property. But only the city can answer that for you. Whether that holds up legally is a completely different question. However, until that is decided, you could be old and gray...
 

wiltshire

2025-07-17 10:21:01
  • #2


The answer surprises me, because special local requirements arise alongside the development plan from the various municipal statutes.
Statutes, according to my knowledge, specify a development plan and are also legally binding.
 

nordanney

2025-07-17 10:21:46
  • #3

Yep. Seen it. But where is the regulation regarding the passive house? I didn’t find it there. That is the clause about district heating.

If the city presents the OP with a different purchase contract, of course other regulations can be agreed upon. But the purchase contract also does not provide for a passive house (in the sample purchase contract).
 

nordanney

2025-07-17 10:30:25
  • #4

By the way, the development plan is also a municipal statute ;)

Above all are the Building Code and the state building regulations. The development plan as a statute takes precedence for the type and extent of structural use, etc.
In addition — neither primary nor secondary — are municipal statutes such as design statutes, parking space statutes, and of course connection statutes. These are supplementary statutes.
As an example: The development plan says what may be built — single-family house, 2 residential units, floor area ratio X. In addition, the design statute says how the house must look — facade material and color, roof pitch, etc. And the next supplementary statute — the parking space statute — says that you need two parking spaces.

It becomes interesting when there are two statutes with different requirements. But that becomes too specific...

However, these do not exist in Ulm. Hence my statement.
 

11ant

2025-07-17 13:37:11
  • #5

How nice that reality occasionally contradicts hyper-greenism. In what way does this non-connectability (legal jargon: "objective impossibility") manifest itself?

Well, time machines do not exist yet, technically construction only takes place after the purchase. What does the contract say in case of non-fulfillment (setting aside the reason): rescission, penalty, ...?


“Suitable” contact persons are only available to a limited extent at “various offices.” Regarding practical suitability (subject-matter competence), it may be necessary to be connected from Pontius to Pilate kind of like the Asterix-style “pass permit” or “application for issuance ...”. The legal suitability of a contact person in an authority, however, is linked to their responsibility, for which there are legal bases and organizational charts. Responsibilities are at most divided into higher and lower levels but are mutually exclusive, thus never duplicated. And the planner may be commissioned with the planning but will not be vested with decision-making powers. Nor can they be sued for performing the activity. It is also common for the building authority at the municipality to serve as the delivery and preliminary examination instance, but the decision on the application is under the responsibility of the district office, which can overrule the vote of the municipal building authority. So the municipality may act as the seller of the plot, your contractual opponent here (and may potentially try to make things difficult for you with the building application) – but if the district decides on the building application, establishing good relations with the responsible person there is significantly more helpful.

From a legal perspective, two things should be examined here: the attitude of the relevant decision-maker (Team Paragraph or Team Reason) regarding the building application (better handled by a construction law lawyer) on one hand, and the enforceability or toothlessness of the passive house provision in the purchase contract (better handled by a contract lawyer) on the other. A law firm with specialists in both areas may be recommended here.

There are indeed quite a few passive house providers, although not every prefabricated house builder offers such concepts. Fundamentally, they are more common among timber constructions than among masonry. What reasons do you have for limiting the provider field to prefabricated house builders?
By the way, who are the neighbors building with (both of these five and those plots that can be connected to the local heating network)?

Ceterum censeo, for me the terms “passive house” and “local heating” only fit together with a lot of friction. Incidentally, one can only scratch one’s head at the political nonsense that on one hand landlords are no longer allowed to conclude a radio cable contract for all tenants, but on the other hand a municipality should patronize the heat energy consumers of an entire development area instead of free consumers burning Meier’s coal from Telekom and Müller’s gas from Vodafone. There are developments that increasingly make me understand non-voters and protest voters :-(
Hoho ho hoho ho, ho hoho hoho hohoho. This dog cannot speak!
 

Mathis.aenni

2025-07-17 14:46:52
  • #6
Thank you very much for your explanations 11ant. I cannot say why the FW connection is not possible on 5 properties (possibly miscalculated). A good point about the final decision being made by the district. The most important question for me remains which document or applicable law the city could refer to in order to reject a submitted building application on the grounds that limit values are not met, which are not cited in any official document of the city/Baupilot (except in the PDF cited by the city planner). In my opinion, such a "decisive" clause should be visible to everyone before purchasing the property (e.g. in the justification for the development plan) without having to laboriously obtain this information from the only contact person at the city who knows these limit values. I am curious what legal experts will advise on this.
 

Similar topics
02.01.2012Semi-detached house - who submits the building application first, wins?29
10.12.2012Terrain elevations in the development plan are incorrect.12
29.10.2013Property reserved, construction financing plan, architect/building permit application21
07.06.2017Permeable traffic areas in the building application17
04.08.2017Building application or building notification15
22.09.2017Telephone construction inquiry rejected13
20.11.2020Wait with the building application because of the child construction allowance1354
28.02.2018Deviation from the development plan in the new construction area is possible118
11.05.2018Construction application costs only 40 euros due to exemption application?27
17.12.2018What is set in stone in the building permit application?10
15.06.2020Period between submitting the building application and moving into the new house11
20.10.2020NRW: Exemption procedure with minor deviation from the development plan18
06.09.2021Forest land plot assessment land use plan / development plan17
09.05.2022Building application due to parking spaces not approved. What can happen?30
10.03.2023Preliminary building approval positive, building application criticized position29
17.07.2023Municipal development plan insufficiently executed, what applies?32
14.08.2023Unclear clause in the development plan but authority does not answer questions23
07.09.2024Notarial Purchase Agreement - No Guarantee for Building Land29
20.10.2024Exception from the development plan for a carport?16
29.07.2025§34 in relation to the development plan; Definition of the immediate surroundings37

Oben