Here, as announced, is the cost breakdown:


0. Preparation
Land
Land 116,000.00 €
Property transfer tax 6,960.00 €
Notary 2,320.00 €
Total 125,280.00 €
Development
Gas 1,000.00 €
Electricity 750.00 €
Fresh water 1,000.00 €
Telekom 500.00 €
Wastewater 1,500.00 €
Total 4,750.00 €

Permit/Surveying/
Preparation

Building permit 800.00 €
Construction road 5,000.00 €
Construction water/construction electricity 500.00 €
Construction toilet 1,350.00 €
Surveying/Cadastre 2,700.00 €
Soil report 1,000.00 €
Structural engineer review 1,500.00 €
Insurance 500.00 €
Total 18,100.00 €
Architect/Structural engineer 30,000.00 €
Total Preparation 178,130.00 €

1. Earthworks
Excavation (720m³)
25,200.00 €
Transport
7,500.00 €
Inspection shafts/infiltration basin
2,500.00 €
Basement
84,500.00 €
Buffer
15,000.00 €
Total
134,700.00 €

2. Shell construction
Shell construction
170,000.00 €
Roof structure and roof
50,000.00 €
Total
220,000.00 €

3. Building services
Gas, water, sanitary
50,000.00 €
Electrical
50,000.00 €
Total
100,000.00 €

4. Interior fittings
Windows
25,000.00 €
Doors
15,000.00 €
Stairs
15,000.00 €
Front door
6,500.00 €
Floor coverings
(material and labor costs)
25,000.00 €
Wall coverings
(material and labor costs)
17,000.00 €
Furniture
30,000.00 €
Lighting
7,000.00 €
Fireplace
15,000.00 €
Total
140,500.00 €

5. Outdoor facilities
Paved driveway 87 sqm
6,700.00 €
Terrace 20 sqm
1,500.00 €
Terrace roof
13,500.00 €
Lawn 153 sqm
770.00 €
Planting
2,000.00 €
Outdoor lighting
3,000.00 €
Carport + tool shed
15,000.00 €
Exterior facade
18,000.00 €
Additional features
7,000.00 €
Total
67,470.00 €

I am grateful for any comments, especially those where I am completely off.
 

arnonyme

2019-04-04 21:28:24
  • #2


Too little, rather plan double. Drainage is also too cheap, overall certainly 15k.



Architect that cheap? Why is the construction road 5,000? Is it 30m long?



Excavation too expensive, disposal way too cheap. How do you come to 720 m³? Consider soil loosening? That quickly adds another 20%. For us, excavation and disposal were about 40k, so you should roughly arrive at the total, depending on soil analysis of course. I find the basement a bit high, but for that, the plans would be good to judge. The basement for me, including basement ceiling, cost about 45k just for materials and about 18k labor.



In this respect, the shell construction is, in my opinion, priced too high; I pay that for the entire shell construction including basement and garage. Two floors to be bricked and a solid ceiling should be considerably cheaper. I have no idea about the roof since we are building with a flat roof. But it should be cheaper; 50k roughly costs my upper floor solid ceiling with sealing and green roof. From experience, a flat roof is usually more expensive than a pitched roof.



Gas, water, sanitary I think fits. Electricity no idea, I pay about 15k but no home automation.



Windows most likely way too low, but for that you’d have to see the plans. For me about 75k with front door and aluminum roller shutters or venetian blinds, all electrically operated. However, wood-aluminum; with plastic you come about 20k cheaper, at least with our window maker. So rather plan double. Stairs depend on what you want, but for 15k you can get something decent. A two-stringer stair with oak steps you can get for 10k as well. No idea about the rest, but seems sufficient. What about interior plaster? That easily costs 10–15k. Screed also completely missing. Another 10k.



Except for the exterior facade, looks plausible. I would rather plan at least 10k more there.

Do you subcontract the trades yourselves, or does the architect take care of that?
 

Cube1984

2019-04-05 09:50:27
  • #3


Thanks for taking the time to give detailed feedback. For some trades, there are already offers (including comparison offers) so I probably have little room there. For other things I’m really missing a big chunk on my side, e.g., windows.

However, I included screed in the shell construction, so it will probably work out in the end.

I’ll try to manage uploading the plans this evening or tomorrow.

For wastewater, we finally paid €4,700.

Edit: we are awarding the contracts ourselves.
 

ypg

2019-04-05 10:17:15
  • #4


With edging too cheap. Anyway: the splash guard around the house and other reinforcements are missing.


I find the figures wrong, considering that you don't have to calculate them as they are fixed by the suppliers and can be inquired. We roughly had to pay €8,000 for everything (including Telekom)...


Too low. Connections cost, rental costs, consumption costs.
Electricity for drying devices can be over €1,000, including the rental.
What about container? Scaffolding?
 

Cube1984

2019-04-05 10:37:36
  • #5


Thanks to you too for the feedback.

As I said, with the development we are now completely at 7,750 excl. Telekom; I am still expecting the invoice, with the amount supposed to be between 800€ and 300€ with simultaneous conclusion of Magenta, let's see.

I find it incredibly difficult to capture every single item. Can flat percentage rates be used as a buffer?

Calculating an independent scaffold certainly makes sense because we are not building with a general contractor.
 

DASI90

2019-04-10 11:55:19
  • #6
But you are building 240 sqm of living space plus a basement?
 

Similar topics
07.10.2014Renounce Telekom connection30
01.01.2016Cost of house connection for Kabel Deutschland and Telekom?37
07.05.2016Buying a shell construction - Experiences21
16.07.2016Telekom connection - line already laid, still have to pay 600€?29
08.08.2016Connection costs for telecom, cable, electricity10
23.09.2016Architect and budget limit... insurance? possibilities25
01.02.2017Duration of completion notification for Telekom house connection22
15.03.2018When is a slope a slope? Basement vs. slab19
20.02.2018Telekom home connection, your experiences. Is Magenta M okay?43
06.11.2018House connection: Telekom does not want to drill through the white tank17
05.12.2018Dispute between telecom and municipal utilities - house connection10
02.04.2019Building plot: Massive fill or better basement with excavation?28
07.06.2020Single-family house optimization and planning (180 sqm + attic without basement)159
28.07.2020Single-family house 160m2 with basement, 500m2 plot108
22.11.2020Floor plan single-family house 180 sqm + basement in Rhein-Main38
28.11.2020Expensive plot + single-family house 155 sqm + cellar KFW40+, financeable?60
22.12.2020Floor plan of a single-family house with a flat roof on a 600m² plot19
24.02.2021L-shaped house on trapezoidal plot34
11.03.2023Fiber optic expansion by 1&1 or Telekom - Who pays for the construction trenches?20
09.09.2024Floor plan design: Single-family house with basement; 560 sqm plot65

Oben