Offer comparisons - reference values, experiences?

  • Erstellt am 2019-04-03 21:35:39

Tassimat

2019-04-04 09:24:42
  • #1
The architect rolls the numbers just like you do. On my architect’s cost estimate, it is boldly stated that prices can deviate by 30%. You can only hope that not every item was underestimated.

Regarding your request to the craftsman:
When quoting prices, you always have to be extremely careful and ask whether the 19% VAT is included or not. Although you are inquiring as a private person, not everyone adheres to the rule of having to indicate this. This could explain the price difference you observed.
 

HeinzBauen

2019-04-04 10:38:28
  • #2


So we are building 180 sqm without a basement and our architect noted about 53,000 for the cost estimate.

Now we have obtained 2 offers and one comes to 46,000 without bathroom furniture and one to 80,000 with complete bathroom equipment
 

Cube1984

2019-04-04 10:48:11
  • #3
correct with 30% variance +/-, I had already calculated +20k. As I said, I will post the listing this evening.

The bathroom was now including VAT but a good point to have another look at it for the other offers
 

Cube1984

2019-04-04 10:50:58
  • #4


The difference is really huge. Is it only the equipment that makes the difference of 34k? Or are there also differences in labor costs? What kind of heating system? With or without ventilation system?
 

arnonyme

2019-04-04 13:13:54
  • #5
So for the region, I don't find that expensive. We have similar areas and I come to about 50k with heating brine heat pump and sanitary rough installation without objects.
 

Cube1984

2019-04-04 18:52:06
  • #6


If I subtract the sanitary fixtures, I end up at 55k, then it balances out again. I think what shocked me was the difference between the preliminary discussion and the offer.
 

Similar topics
19.07.2018Draw the plan yourself? Do you necessarily need an architect?11
18.02.2011Architect totally messed up - experiences?17
30.09.2012Final invoice architect13
27.10.2013Architect --> Agreements? What is that?21
16.04.2014Cost of soil survey - Does the architect pay or do we?12
16.09.2014Termination of collaboration with architect - demands excessive fee28
01.10.2014Collaboration with an architect - how does it work properly?22
25.02.2015Planning / Architect, involvement of specialist planners for the approval plan10
10.04.2015Cost estimate architect single-family house. Your assessment44
26.04.2015Semi-detached house architect or general contractor / prefabricated house or solid construction13
27.12.2015Who has built with an architect? Experiences??85
11.09.2015Building a garage on the boundary is not possible according to the architect.11
17.11.2015Is an architect really that expensive?46
05.04.2020Developer or architect - costs43
07.03.2016Various dimensions architect execution drawing12
23.09.2016Architect and budget limit... insurance? possibilities25
17.04.2017Civil Engineer vs. Architect17
13.06.2017Architect or developer? Which is more affordable?13
10.11.2020The architect is wrong with the estimates. And now?29
22.01.2022Check cost estimate from preliminary draft35

Oben