House construction company/legal required changes to the building contract

  • Erstellt am 2016-08-06 11:10:11

ONeill

2016-08-09 09:11:35
  • #1
Strangely, it was with some of my providers at the turn of the year. We had searched before the turn of the year.

Strange.
 

markus2703

2016-08-09 09:17:09
  • #2
I also didn't believe it at first, but the increase actually took place with us on 31.08. - prices on the homepage were then higher.
 

Uwe82

2016-08-09 09:19:10
  • #3
Smaller GUs can also be more lenient with price increases. Our company usually raises prices at the end of January. However, our consultant still gave us until the end of February to sign and even continued a discount promotion that was actually supposed to end at the end of the previous year. So it can also be flexible.

Isn't [Stadt & Land] a franchise system? Such things should be somewhat more flexible there, compared to when a large corporate headquarters dictates the price change on a fixed date. In any case, I would not let myself be pressured by that. Good information, but everything must be checked beforehand. And if it isn’t and one does not engage in negotiations about the cutoff date, then one either has to bite the bullet and pay more or find someone else.

For one of the biggest investments in life, you must not be rushed!
 

DG

2016-08-09 16:59:45
  • #4


The example does not quite fit. The surveyor is commissioned by someone - client, architect, or general contractor - to prepare the site plan. The client (!) receives the invoice - whether this is settled between other construction parties internally is pretty irrelevant to the surveyor or any other external provider, since I do not know the contractual arrangement between the general contractor and the client and cannot verify it anyway. The claim is always directed at the client in case of doubt.

Best regards
Dirk Grafe
 

Bauexperte

2016-08-09 21:56:10
  • #5

I was referring to the fact that the lawyer preferably does not see the TE liable for a denied BA; logically, this logic would then also have to be applied to the surveying service.

When I wrote that, I didn’t yet know that Stadt & Land would like to see 10% of the contract sum for that.

I need current documents for this provider, then this won’t happen to me anymore ... until next time

Rhineland greetings
 

DG

2016-08-10 00:27:16
  • #6


Without having read everything in detail, I also consider 29 pages of changes to be excessive, unless the contract actually has such extensive defects that justify it. However, some of what the lawyer writes does not, in my opinion, correspond to building regulations law, because the builder does not get completely released from liability there for good reason – especially not on their own property.

The lawyer naturally tries to minimize or even eliminate all risks for the builder; whether she actually succeeds is another matter, because I will now claim from my well-founded layman’s opinion (note, this is not legal advice!) that the building application cannot be formulated as a contract for work. This may work in 99.9% of cases in practice because there are no insurmountable obstacles, but occasionally there is no building permit (e.g. contamination, neighbor sues against construction and/or zoning plan and wins, zoning plan unlawful, access path not secured, city exercises pre-emption right, etc. pp.) – and how is the general contractor supposed to remedy this as part of a contract for work? Some things can be solved with time and money, but some simply do not work because the legal issues cannot be resolved.

And then, in case of doubt, the question is who will pay for the effort up to that point. As a contractor (surveyor) you may be left with the costs if you cannot prove who gave the order and when. Some things are arranged by phone, which is problematic if damage occurs – also for the builder or general contractor.

And to bring the subject back to the core question: in my opinion, the planners/general contractors take a big risk with their statements/promises regarding the trade "building application," because below about €1 million construction cost (which is understandable because the builders do not pay/tolerate it) little to no effort is made to assess the risk of a building permit not being granted. The building application is simply submitted and possibly corrected afterwards. This also explains the 10%; for some large special projects, the building application could be set at +25%, because the building permit is a major, if not the greatest hurdle.

So what happens: with a house value of €250,000, the disputable amount is 10% = €25,000; this halves because one is likely to settle regardless of how the lawyer formulates it, so statistically €12,500 is lost by the general contractor, from which the rest must/can pay the effort – including the surveyor! – of a construction project (trade) that ultimately does not lead to a building permit.

However, if he does not take the risk "building application," his business model is broken.

Best regards
Dirk Grafe
 

Similar topics
15.02.2011Building permit application12
10.12.2012Terrain elevations in the development plan are incorrect.12
15.06.2015Garage - Building Application - Confusion36
28.11.2024Neighbor's lawsuit against approved building permit46
16.01.2017No building permit as long as the land is not developed?10
04.08.2017Building application or building notification15
20.11.2020Wait with the building application because of the child construction allowance1354
28.02.2018Deviation from the development plan in the new construction area is possible118
11.05.2018Construction application costs only 40 euros due to exemption application?27
14.10.2018Building application - delay due to neighbor's lawsuit - experiences?21
17.12.2018What is set in stone in the building permit application?10
04.01.2019Terrain modeling different from the building application - allowed? (NRW)36
25.11.2019Exemption procedure or building permit40
20.10.2020NRW: Exemption procedure with minor deviation from the development plan18
15.08.2021Duration until the issuance of the building permit in BW57
30.07.2021Is building without a building permit possible?26
30.11.2021Fee notice for building application57
22.05.2022Tips for Waiting for Building Permit26
10.03.2023Preliminary building approval positive, building application criticized position29
17.07.2023Municipal development plan insufficiently executed, what applies?32

Oben