Exemption procedure or building permit

  • Erstellt am 2019-11-21 12:05:02

dab_dab

2019-11-22 08:10:37
  • #1
We had a sloping plot and thought we had considered everything; the municipality approved it in the clearance and issued the building permit before Christmas.

Now, after Christmas, the district office wrote: Not approvable like this (average heights in terrain profile, max. height of retaining walls, etc.).

End of the story: Building application with deviations submitted to the district office and in about 8 weeks everything, including all involved authorities, was properly arranged and approved.

At first, I was annoyed about the time loss; in hindsight, I am really glad to have the building permit. In the new development area or around it, there is always someone who on the one hand seems to have a lot of time and on the other hand is very curious to somewhat annoying.

Costs are manageable. The decisive factor is not your actual construction costs but a percentage of a fictitious construction sum per enclosed space set by the district, which fortunately has little to do with the real construction sums. In the end, including deviations, just under 1000€.

Back then there was a construction stop with neighbors. So it’s not just an empty threat – insofar per building permit.
 

fragg

2019-11-22 08:37:39
  • #2
Demolition is the worst case. For us, the heat pump would have been a problem; the construction company based the noise calculation on existing buildings, but the authority referred to construction plots and potential buildings. We had one parking space too few. We did not apply for the outdoor seating area of the granny flat; the authority read from the building plan that a permit-required terrain modeling was taking place here. So it would have caused problems that would have been significantly more expensive to solve than the building application cost.
 

nordanney

2019-11-22 12:42:58
  • #3
But these are fundamental things that every architect MUST recognize. That’s what they are paid for. I also can’t say, "OOPS, one more floor than allowed – we didn’t see that." If there are exemption procedures, I would always use them. Exception: You really have to cheat and try to squeeze your house into the development plan at all costs. For us, it was never checked either – what should be checked anyway. The office does not inspect, does not measure, and therefore does not come out (at least for us in NRW).
 

desixtor

2019-11-22 13:00:15
  • #4
The problem is the retiree with a dog who is too bored and walks through the construction areas. Or the dissatisfied neighbor who tries to transfer his bad mood to others.
 

Yosan

2019-11-22 13:37:21
  • #5
So apparently everyone here has [Nachbarn /Spazierengehende Rentner]...
 

11ant

2019-11-22 14:46:45
  • #6
Or a neighbor with a denied exemption for his special request (dormer wider or the like) then wants "equal injustice for all" and discovers the new hobby "millimeter man combined with block warden." Formulated as a farmer's rule: "In case of doubt, keep distance from the freestanding structure if there were complications with approval at a neighbor."
 

Similar topics
15.02.2011Building permit application12
27.09.2018Cost of building permit in exemption procedure, new construction11
17.12.2014Building application "deferred". What does that mean?19
15.06.2015Garage - Building Application - Confusion36
28.11.2024Neighbor's lawsuit against approved building permit46
18.03.2016Influence of the neighbor in building permit18
16.01.2017No building permit as long as the land is not developed?10
01.02.2017Building application is becoming increasingly complicated!20
04.08.2017Building application or building notification15
20.11.2020Wait with the building application because of the child construction allowance1354
11.05.2018Construction application costs only 40 euros due to exemption application?27
21.06.2018What must be included in the building permit? Legal certainty?19
18.09.2018Immission protection concerns self-service gas station - building permit?20
14.10.2018Building application - delay due to neighbor's lawsuit - experiences?21
04.01.2019Terrain modeling different from the building application - allowed? (NRW)36
15.08.2021Duration until the issuance of the building permit in BW57
30.07.2021Is building without a building permit possible?26
30.11.2021Fee notice for building application57
22.05.2022Tips for Waiting for Building Permit26
28.06.2024Building permit - is a lawyer useful?12

Oben