So, dear forum members

our first offer discussion is behind us. We have now received our first offer for our dream house. The offer comes from Hanse Haus.

Hanse Haus offers a 1.5-story house with a gable roof and a 35-degree roof pitch as well as a rectangular bay window in the living room. The living area is approximately 175m2... the knee wall in the attic is 1.4m high. As for the equipment, we think we have chosen slightly upscale standard with electric shutters, various additional windows, larger front door, etc. There is a shower toilet and a large bathroom... we currently waived the home automation, but it is possible that I will still include the wiring for it. It will be built to Kfw 40 standard with gas and solar. Possibly we will switch to Efficiency Plus with photovoltaics, battery storage and air-to-water heat pump... knowing full well that this will never pay off.

The total price for the house is now according to the offer 324,000€ including foundation slab and turnkey delivery. What do you think about the price... is it reasonable?

We still have comparison appointments... nevertheless I would be grateful for a rough assessment!

Best regards
 

Caspar2020

2017-04-02 22:04:28
  • #3


Is it move-in ready? Or what is still missing?
 

werners81

2017-04-02 22:16:06
  • #4
Is move-in ready... however, everything is wallpapered and painted white! We still have to adjust the roof overhangs! On both the eaves side and the gable side, 15 cm must still be added... whatever that may cost!
 

Curly

2017-04-04 14:24:14
  • #5
Are floor coverings included as well? If everything is included, then I find the price quite normal.

Best regards
Sabine
 

werners81

2017-05-12 23:10:52
  • #6


Hello again

So we have now finalized our house. We have arrived at a KfW 55 house in timber frame construction. We have planned about 174m2 with a 38 degree gable roof and a 1.4m knee wall. Insulation with wood fiber insulation boards and mineral wool as well as 240mm of jute in the roof.
Technically, we have app-controlled electric shutters, photovoltaic, lwwz thz404 with controlled residential ventilation, large lift-and-slide door in the winter garden bay, and various other things. The price still includes two barrier-free showers and a 9x3m prefabricated garage. Additionally, the floor coverings are tiled on the ground floor. Painting and fleece wallpapering as well as floor coverings in the attic are to be done on site. However, q3 is handed over filled.

What do you think, is the price of about 320,000 euros realistic or should I still do something?
 

Similar topics
13.04.2012Planning a gable roof and roof slope17
14.10.2014City villa or classic gabled roof house? Advantages? Costs?51
23.02.2016Photovoltaic + Battery - Which System - Experiences?17
06.04.2016Financing for 15 or 20 years? Photovoltaics via KFW?10
14.04.2016Detached villa with "gable roof" or flat roof37
13.09.2016Gable roof as usable area12
12.10.2016Kniestock lowered afterwards34
10.06.2018Build a house with a knee wall 75cm high or two full stories? Your opinion?17
12.01.2019Will the Energy Saving Ordinance from 2021 make new construction unaffordable?27
26.02.2019Floor plan - 135 sqm, 1.5 storeys, gable roof138
27.12.2019Low ridge height results in a low knee wall55
08.05.2020Construction costs city villa - gable roof17
24.10.2020Planning of a single-family house approximately 190m² with a gable roof, basement, double garage11
11.01.2021Bungalow expansion to single-family house - costs, KfW funding & planning12
07.02.2022Survey of saddle roof knee wall height38
10.10.2023Land in sight, is house construction financially possible?117
24.03.2025Small Bungalow Floor Plan - Optimization Potential?106

Oben