Construction diary of the new build of a city villa with garage

  • Erstellt am 2021-01-27 21:26:05

dynaudio79

2021-01-28 20:48:14
  • #1
Nope. He was only on site the day the floor slab was supposed to be laid. I fulfilled my duty as the client and expressed my concerns regarding the driveway. And that beforehand. So I'm in the clear, right?
 

Tolentino

2021-01-28 20:54:48
  • #2
I would see it the same way. The problem is, even if you are right, when it costs money, companies are stubborn at first. And then the question is, when do you want to have your house finished... Really annoying story.
 

dynaudio79

2021-01-28 21:24:24
  • #3
Sorry, but I am not paying an additional 6500 euros for something I have not caused. Evidently...
 

Lumpi_LE

2021-01-29 08:42:03
  • #4
not nearly as much dropped as forecasted. Why was there actually a concrete pump there when there is no reinforcement yet. Makes little sense. What does the contractual relationship look like? Simply put, extreme case, if you ordered the concrete and the offer states that the client provides access, it would be your problem.
 

dynaudio79

2021-01-29 12:30:36
  • #5
As already mentioned, they wanted to pour everything at once. When the concrete pump had left again, the guys also started again. Concrete was ordered by the construction company.
 

dynaudio79

2021-02-01 18:39:26
  • #6
The second attempt at the foundation slab action has now also taken place. Again, the site manager called me around noon to say they had to stop. This time the pump broke down before it could be started. But the concrete mixers were able to drive onto the property and so two trucks were able to unload, allowing at least 90% of the foundation to be poured. For the third appointment, a road closure is now being requested, which I am supposed to organize. So something is definitely not right. The guys ran off again this time and did not finish the formwork or install the reinforcement. That would be nonsense, right?
 

Similar topics
21.10.2011Floor slab insulation "Yes!" or "No!"14
18.09.2012Construction of a base slab with frost skirt but without foundation10
31.05.2015Wastewater pipe concreted in the floor slab at the wrong location29
14.09.2012House financing - house, garage, and foundation slab approx. 290,000 EUR11
26.10.2012External perimeter insulation floor slab, basement mold risk11
21.11.2013Is the floor slab still possible this year?15
15.07.2014Foundation slab for Danwood bungalow? Company for complete works?11
23.11.2014Stone throw on foundation slab - builder's liability insurance?16
15.06.2015Base slab or strip foundations for garage12
07.09.2015Minimum distance from the base plate?11
11.09.2016Base plate - construction/insulation etc. - experiences please!10
20.08.2016Base slab vs strip foundation15
11.10.2016Reinforcement / Armature visible31
06.10.2016Base plate with defects?22
18.08.2017Base plate ready - construction supervisor absent20
18.07.2019Does the insulation under the floor slab have to extend to the formwork?14
17.08.2019Base plate - Reinforcement steel is sticking out12
28.10.2019Base plate - reinforcement visible from the side15
16.04.2020Pour the ground slab in sections?19
17.10.2020The base plate was cast too large - it has now been shortened - is that okay?48

Oben