Behavior/Consequences towards Construction Company

  • Erstellt am 2022-07-17 13:40:00

Axolotl-neu

2022-07-17 20:39:21
  • #1
Why did you do it? No, the contract says December 31, 2022. Now I ask from the contractor’s perspective: Why should I finish earlier than what you explicitly signed in the contract? If it was so important to you, dear customer, why didn't you say so and we would have included it in the contract? Feel free to get legal advice, but the contract = the written agreement is clear.
 

Neubau2022

2022-07-17 20:43:37
  • #2
How is August 2022 supposed to be completed if there isn't even screed in yet? The drying takes about 4-6 weeks. And the rule is that after the screed is poured, it takes about 3 more months. So you could expect December and can safely cross out August.
 

allstar83

2022-07-17 21:24:20
  • #3
There are screeds which are walkable after a few days. But they cost.
 

Neubau2022

2022-07-17 21:37:52
  • #4


I do not assume that this screed is included in the contract :cool: Screed alone is not everything. As I said, nothing will happen before December. Prepare yourselves for that.
 

allstar83

2022-07-17 22:13:50
  • #5
Electricity for fan heaters cost us a few thousand euros... I just wanted to suggest that this option could also be considered. Calculate the rent for a few months against it and it fits again.
 

bauenmk2020

2022-07-17 22:26:48
  • #6
Has anyone in this forum addressed this question so far? Unfortunately, some good forum members who could have contributed better to clarifying this are no longer present. Early house acceptance is not necessarily advisable - without professional support. What contact do you have with your site manager? He is actually the one coordinating the resources. Maybe you can also find out in a conversation where it is currently lacking? Staff, materials, etc. Otherwise, I would start looking for an apartment. Unfortunately, you don’t get sympathy as someone building a house and it just takes longer. That’s just how it is. Maybe there is a way to store furniture etc. in a room in the new house. And if the floor in this room is installed later, it doesn’t matter – at least the screed has plenty of time to release moisture.
 

Similar topics
29.01.2014Cost saving/basement/affordable tiles/sealed screed?13
13.04.2017Screed with gold sand17
28.04.2016Order screed - plaster14
27.05.2016Plastic fittings/water pipes and insulating underfloor heating beneath screed?40
29.07.2018Perimeter insulation under the floor slab and still XPS under the screed?28
31.10.2016Heating the screed with the utility provider?!12
29.11.2016Front door only burglary protection / better materials - plaster, screed?10
02.02.2017Is ventilation/drying after installing screed/interior plaster sensible?15
05.08.2017Screed necessary? Unfinished but insulated attic23
11.09.2017Raise the planned click vinyl flooring or increase the screed?12
24.07.2018House 1930s reddish screed and linoleum12
06.11.2018Recess in the screed 5 cm high - How is it done?10
09.10.2019Screed and tiles already laid but no heating14
07.05.2020Cracks in the screed. Problematic?25
28.08.2020Urine on wall / on and possibly under screed16
22.12.2020Is it allowed to lay tiles on fresh screed?12
19.03.2021Floor insulation not glued/sealed to the screed27
25.02.2022Too much moisture in the single-family house after screed installation? Risk of mold?49
21.10.2022Screed vs. Fast-drying Screed12

Oben