Behavior/Consequences towards Construction Company

  • Erstellt am 2022-07-17 13:40:00

Kathi92

2022-07-17 18:06:08
  • #1


The contract states "Completion by no later than 12/2022." At the time, we said we could not sign under that condition. The builder then said that they have to include that pro forma because of the lockdown and delivery difficulties. Because they cannot influence that under the circumstances. Which we could, of course, understand. But we received a construction schedule which both we and they adhere to (construction completion May 2022), this was signed and also submitted to the bank. The bank also followed the construction schedule.

There are no delivery difficulties (the warehouse is stocked with our materials) nor a lockdown. The deviation from the construction schedule is therefore without basis.

But then it’s apparently one statement against another, which helps no one, least of all us.
 

bauenmk2020

2022-07-17 18:07:15
  • #2
I just guess that the general contractor is building another house and "pressure" is being applied there. Thus, all resources will be tied up there and you ("those who are not shouting the loudest yet") will be sidelined. Currently, it is the case that the craftsmen are sent from one construction site to another. Material is then not completely available or someone has to make follow-up calls. But if everything is in stock at your place, the general contractor should actually be interested in finishing the construction so that his warranty period starts. However, I assume that he currently has to "fix" something elsewhere. You should find out where that could be.
 

Axolotl-neu

2022-07-17 19:20:50
  • #3

That basically says everything and the thread could be closed. Contracts must be adhered to, and therefore the general contractor has until the end of the year. Nobody cares about all the talk around it anymore. Stupid, but that's how it is.
The construction schedule is a plan in this regard. It is attributed to Einstein, who is said to have said: Planning replaces chance with error. In this respect, it remains with the completion date between you and the general contractor agreed upon in writing, no later than 12/31/2022.

Sorry. At first meant.
 

Neubau2022

2022-07-17 19:28:43
  • #4


1. Are you professionals that you don’t have an external construction supervisor? If not, that’s negligent. I hope you’re lucky and that the general contractor at least works diligently. Important aspects include the execution of the foundation slab and installation of the underfloor heating.

2. It’s like with us. Construction time guarantee 10 months, so end of September 2022. The first construction schedule was with house handover in May 2022. That was quickly buried. The second then end of July 2022, which also won’t be met due to the geothermal heat pump. We are now terminating the apartment as of 31.10.2022.
 

Kathi92

2022-07-17 19:33:51
  • #5


Thank you for your answer!

I don’t quite see it the way you do. Especially since oral side agreements (“all the talk around it”) can very well be legally effective, especially since we have not established a written form requirement. Why should I voluntarily sign the contract with that clause if then I have no place to live for 4 months? At signing, we said it MUST be finished by summer at the latest. That was agreed upon. Along with the signed construction plan.

We will contact a lawyer tomorrow and have a formal letter drafted. Maybe that will have an effect.
 

hauskauf1987

2022-07-17 19:48:40
  • #6

That's how it is
You have zero leverage
 

Similar topics
16.06.2011Conclude a construction contract under reservation?10
13.09.2012Feeling pressured into a contract, is that normal?17
29.09.2011Is construction pre-planning without signature / contract legally valid?12
16.05.2015Contract unclear: humus earth collectors10
23.08.2015Construction financing with a fixed-term contract13
04.07.2016Building without a contract - Concerns?39
10.09.2016Construction financing and contract with the developer24
28.09.2016Question about early repayment and clause in the contract41
28.05.2017Plundering the Riester contract - for less need for credit?16
16.08.2018Civil engineering works without a contract - normal, experiences?10
11.10.2018Waste on the construction site - What is tolerable?138
04.01.2022Architect, contract according to HOAI 2013 - refuses to provide service36
06.06.2019Completion date in General Contractor Agreement - Wording assistance62
05.08.2020Contract for land purchase - obligation to build within 2.5 years18
11.11.2020Cancellation of a contract with a plumbing company24
09.05.2021Price adjustment clause in the contract with the general contractor18
30.03.2022Terminate the contract with the general contractor "early"22
27.01.2024House purchase through agent, now contract terminated18

Oben