Behavior/Consequences towards Construction Company

  • Erstellt am 2022-07-17 13:40:00

WilderSueden

2022-07-17 22:45:07
  • #1
The problem with oral agreements is proving them. If you now also have a written contract that claims exactly the opposite (finished in December), that does not necessarily help your position either.
 

ypg

2022-07-17 23:27:33
  • #2
Yes, communication often fails. Small construction companies often do not have a GeZi pool, the office staff cannot answer questions about the construction, much is done via mobile phone because very few houses are built at a desk. However, the site manager should be reachable during business hours.

Does the bank have anything to do with the construction schedule? You only pay when the partial demand (I have actually forgotten the technical term now) comes in writing and not what the schedule indicates. For example, we didn’t have a construction schedule at all, precisely for this reason, because clients can get quite nervous and the general contractor couldn’t commit.

I did not understand this point: had you already terminated the apartment "back then"? That would have been quite early, right? Over a year in advance?

Yes! It was pointed out that it is difficult to find craftsmen.
I add the fact that the electricity for the drying devices will probably no longer be paid for by the general contractor, which they had offered.

It is understandable that the general contractor is patching holes. Very likely he has taken on one more project than the capacities allow.

Everything is already bad in your situation. However, apparently from the start a big bundle of naivety was involved. The general contractor has December on the schedule.
You are not the only ones, not the first or the last. Freight forwarders have specialized in storage and holiday apartments offer special prices for a quarter’s rent.
 

Hausbau0815

2022-07-18 05:48:36
  • #3


You can save yourselves the trip to the lawyer and the money. You have no legal recourse against the general contractor. A contract is a contract. And it states the completion date as 31.12.2022. Nothing else matters. The lawyer charges based on the value in dispute. For you, that will likely be the entire contract value and quite a significant amount. I know what I’m talking about, as my legal disputes have already cost a lot of money.
 

HilfeHilfe

2022-07-18 06:27:45
  • #4


Hello,

sorry to have to say it so harshly. But December is still 5 months away. You signed it that way and should have planned accordingly. The company has plenty of stories to explain why they are not finished earlier (material shortages, craftsmen, etc).

You can save yourself a lawyer.
 

Yaso2.0

2022-07-18 08:02:38
  • #5


Oral side agreements should certainly be sufficient when it comes to things like changing the door hinge or other rather unproblematic matters. For contractual things, in my opinion, it is simply very very difficult to prove these side agreements if the general contractor suddenly can’t remember them or denies them. I also want to point out, what do you gain from it? A lawsuit won’t proceed faster, and finding substitute craftsmen to complete the unfinished work of the predecessor will probably also be very difficult!

We also received a construction schedule, but this was never a binding handover agreement. We had about one month delay according to the construction schedule overall, but a point landing, as was agreed in the contract.

As much as it pains me, I see it like the other participants, that you will have a very hard time legally enforcing anything.

I would now rather try to build pressure. I’m normally not the type to exploit circumstances for something, but I would still bring into play that these circumstances affect you emotionally and accordingly your pregnancy etc. Sometimes you get further with the waterworks than with factual arguments.

I’m experiencing it right now with our garden and landscaping contractor.. Our construction site has now been stopped for a week because another client is crying.. His wife wouldn’t move in earlier until everything was finished. And now all of them are over there and will only come back to us in the middle of the week..
 

hanse987

2022-07-18 08:18:48
  • #6
For the money a lawyer costs, I would quickly get a construction supervisor/expert. I think you would benefit more from that.
 

Similar topics
16.06.2011Conclude a construction contract under reservation?10
13.09.2012Feeling pressured into a contract, is that normal?17
29.09.2011Is construction pre-planning without signature / contract legally valid?12
04.07.2015House contract with financing condition, lawyer wanted10
16.05.2015Contract unclear: humus earth collectors10
23.08.2015Construction financing with a fixed-term contract13
04.07.2016Building without a contract - Concerns?39
10.09.2016Construction financing and contract with the developer24
28.09.2016Question about early repayment and clause in the contract41
28.05.2017Plundering the Riester contract - for less need for credit?16
16.08.2018Civil engineering works without a contract - normal, experiences?10
04.01.2022Architect, contract according to HOAI 2013 - refuses to provide service36
06.06.2019Completion date in General Contractor Agreement - Wording assistance62
11.04.2020Construction law - hire a lawyer or not yet16
05.08.2020Contract for land purchase - obligation to build within 2.5 years18
09.05.2021Price adjustment clause in the contract with the general contractor18
30.03.2022Terminate the contract with the general contractor "early"22
27.01.2024House purchase through agent, now contract terminated18

Oben