Acceptance, what particularities should be noted?

  • Erstellt am 2016-11-23 13:37:38

andimann

2016-11-23 16:48:36
  • #1
Hi,



The windows are still dirty and covered with foil (the topcoat is currently being done). However, I have already informed the general contractor that the windows will only be accepted after the final completion of the plaster and the removal of the scaffolding. Otherwise, I risk the scaffolding builders scratching the window during dismantling.

But thanks for the hint!

Best regards,

Andreas
 

Mike29

2016-11-23 17:56:45
  • #2
From personal experience: Take the time to check whether the individual room controls are operating the correct valves/heating circuits. For example, we wanted to heat the bathroom, but the playroom of our little one always got nice and warm because the heating circuit was on while the ERR was measuring in the bathroom. The other way around as well, the playroom was turned down because it was too warm, and the bathroom stayed cold.
 

Bieber0815

2016-11-23 22:59:48
  • #3

That is the most important thing!

Otherwise, besides what has already been said:
- Site cleared?
- Meter readings and meter numbers legibly noted
- Which documents are to be handed over? Operating instructions? Certificates?
- Keys?

What else we had:
- Labelling of the circuit breakers partly incorrect (you have to notice that first)
 

Payday

2016-11-24 00:30:51
  • #4

It was wrong for us too. You have to figure this out first when you have underfloor heating. At first, we thought individual rooms wouldn’t work until I figured it out. This was already 2-3 weeks after acceptance, because before acceptance, all rooms got warm when all regulators were turned up. The electrician came by, fixed the plumber’s mistake and swapped the valves in the distribution cabinet once. And that was that.

You will have a hard time including the windows in the acceptance in spring because a lot can happen to the windows in the meantime. If it doesn’t work out, check the windows for defects and when the craftsmen come in spring, have them confirm the windows are free of defects beforehand. If something then happens, the craftsmen are responsible again. Of course, you can only accept the windows if they are free of the protective films beforehand. Make sure to also check from the outside whether there are already scratches. The front door frame is also important because it has been heavily exposed (the sash itself often comes only at the end) and in the end is the first thing every visitor sees.

With many defects, repairs are often not economical. Start thinking about what money/extras or similar you want for small cosmetic defects. Properties are usually worth more than cash since the companies can get these much cheaper and their own employees don’t cost 100€ per hour (which is usually charged to you). Examples of extras you could negotiate during the final inspection: pleated blinds, entrance platform, shower door, contributions for garden/paving work, or small things like “having all windows cleaned.” This of course depends on what the construction company itself can provide (or its subcontractors).

What kind of long list do you have with the electrician that you can already write a story about it?! Our neighbors had problems with the radio blinds. Our guys then knew how to connect them. At our acceptance, one socket was missing (the blank cover was screwed on), and one switch was stuck for a roller shutter. Both were replaced in 5 minutes. Additionally, two switches were changed so that other lamps come on when activated (our wish, not a fault). The electrical foreman was very satisfied after apparently getting no praise from the company boss on previous sites.

What you should also pay attention to: silicone! Look everywhere where silicone is stuck. If the stuff is everywhere like with us, have it properly removed, explained to you, and ideally get the cleaning agent for it right away. You don’t want to end up with a hardcore chemical that ruins the new tiles immediately.
 

fach1werk

2016-11-24 09:11:09
  • #5
A big thank you to all of you from Gabriele, who benefits greatly from this thread because today is acceptance day. I have printed out the text from Otus11 and am taking it with me.
 

andimann

2016-11-24 09:24:20
  • #6
Hi,


The problem will now be solved, the exterior plaster is finished, the windows are without film and they will also be cleaned. The threat must have worked. Yes, I would have accepted it, whether the general contractor wants to or not. At an acceptance, the customer calls the shots, not the supplier. The supplier must prove that everything has been done correctly. If he can’t do that because the windows simply are not in an inspectable condition, there is no acceptance for that. Period, end of story. Would you take over a completely dirty car, still covered in transport films??? Why should I do that with the house?


Quite simply, the guys are not quite finished yet. All open points were then a long list last week. But that is slowly getting better...

Thanks to you all and if anyone has further tips, always send them in.
I will then make a list out of it and make it available to the forum.

Best regards,

Andreas
 

Similar topics
15.10.2013electric roller shutters / switch17
27.02.2015Burglary-proof windows?33
03.06.2014Interior design - windows14
07.01.2018install electric roller shutters or just have them prepared22
16.01.2018Is an extra charge for colored windows realistic?19
18.06.2014Inspector defect identification, determination of window installation10
18.05.2016Help needed with window arrangement!32
27.05.2015Huge problem with condensation on the window34
21.05.2015Can roller shutters with switches be retrofitted for wireless control?14
03.10.2016Reed contact alarm system window. How did you solve that?12
21.11.2018Switch for roller shutters on the window or on the door?38
21.12.2018Roller shutters with a switch and central timer, is that possible?23
20.02.2020What does the electrician do during the shell construction phase?19
23.03.2020Building law: Electrician refuses to continue78
05.08.2020Electrical installation - Retrofit switches/buttons wirelessly26
20.01.2021Moisture seeps through the floor-to-ceiling windows in the new building34
12.02.2021Retrofitting FI switches, older electronics18
28.03.2022Replace switch with light - wiring13
09.07.2023Electrician Cost Estimate - New Installation22
29.01.2024How to make windows opaque?29

Oben