Where did it explode for you? Problems during house construction.

  • Erstellt am 2019-10-27 08:01:44

haydee

2019-10-28 09:05:09
  • #1
Since we built with a general contractor, there was little involvement in coordinating the craftsmen. All trades worked well and reliably, except for the floor installer. Considering what they delivered, they should hand in their journeyman certificates.

However, we also felt the effects of the boom. The tinsmith who carried out the work on the house was supposed to waterproof the roofs of the existing buildings and connect them to the retaining wall. No, that's too much work for him - no desire. He said that literally. That was on 10/4/17. In February 18, we finally got someone through connections, and he finished in September 19.
 

wurmwichtel

2019-10-29 20:54:59
  • #2
- Concrete construction (reinforcement knowingly installed incorrectly, second time he wanted to do the crap wrong again) - Bricklayer (wanted to omit the horizontal barrier) - Electrician (delivered wrong switch program, electricity not checked for proper functionality -> burnt cables, non-functional PE, agreements not adhered to) - Sanitary/Heating (handles of shut-off valves placed between pipes, pressure tests not done, drains installed unreachable behind heating system, vent pipes laid in the middle of the room) - Plasterer (walls plastered crooked and uneven - bulge up to 1cm over 70cm, resin plaster used instead of agreed mineral plaster, windows not taped and therefore scratched) - Screed layer (laid 2cm more than calculated in the attic, main contractor refused static proof) I can't get it all together anymore. But if the main contractor shows up at my place again, I'll bury him on the property - it's big enough. However, I would still say that the main contractor is an exception. Sad is only the fact that he massively advertises both on radio, on YouTube, and with so-called construction advisors.
 

Mottenhausen

2019-10-30 10:05:02
  • #3
Things like:

- Tolerance of the screed layer installer --> "is ok and according to DIN" is not sufficient for the required flatness from the sectionally self-contracted tiling trade: expensive follow-up costs for leveling/sanding the "bumpy" screed

- Many things are not contractually defined precisely enough: for example, light reference value for exterior wall paint or freestanding bathtub (according to contract) does not automatically include a freestanding faucet, even if placed in the middle of the room --> follow-up costs everywhere, which add up

- Sanitary sample selection: significant surcharges by the executing company and the general contractor on the already not cheap prices in a bathroom equipment specialty store. This results in partly exorbitant prices for the sanitary fixtures, which are justified by the "installation effort." Ridiculous!

- Discussion about "what exactly is Q3 on walls and ceiling?" Since DIN only applies to plastered walls and drywall, not to filigree ceilings. Here too, the contract should have been formulated more precisely, e.g., "Ceiling Q3 - fully skim-coated and fully sanded" instead of just "Ceiling in Q3."

- Overall, I would prefer to include more things in the house construction contract up to the readiness for occupancy (painting work, exterior window sills at terrace doors, etc., etc.), because before contract signing the surcharges are fair (so you don't go to a competitor), all samples AFTER contract signing are, in my opinion, overpriced.

- Overall, everyone advised us: no matter how well you plan, there will always be unexpected and annoying follow-up costs, i.e., you only have one chance: plan financial buffers, more buffers, and even more buffers. Then you can stay completely relaxed.
 

Yosan

2019-10-30 12:24:47
  • #4
it certainly depends on the construction partner. So far, I cannot confirm this from our perspective, for example.
 

haydee

2019-10-30 13:05:04
  • #5
Me neither. We usually settled accounts directly with the craftsmen.
 

Mottenhausen

2019-10-30 13:52:57
  • #6


Unfortunately, that wasn't possible with all trades...

Plumbing was the negative exception here as well.
 

Similar topics
28.02.2013Heat demand calculation according to DIN 1283112
22.12.2015Is natural stone heating in combination with a photovoltaic system reasonable?16
29.01.2014City villa floor plan / Feedback on static analysis, arrangement28
24.03.2014Heating proof: Heat load calculation according to DIN 12831 or DIN 4708?10
12.06.2014Walls of a new single-family house, ground floor runs crooked, defect correction construction defect19
12.01.2015We want to build - decision support floor plan17
10.09.2015DIN 4109 Noise - What is to be considered?13
06.10.2015Correct formulation for a waterproof basement11
28.11.2016Is sound insulation according to DIN standard 4109 relevant for building permits?16
09.11.2018Is installation of surge protection according to DIN VDE 0100-443/543 mandatory?15
18.10.2018Construction costs for terraces, etc. in cost estimation according to DIN 2719
14.05.2020Sound insulation VDI Guideline 4100 & DIN 4109 in prefabricated house construction49
24.11.2020Heating load calculation & layout plan DIN: Is a new calculation necessary?41
27.06.2023Is sound insulation according to DIN 4109-1 sufficient for a mid-terrace house?19
15.12.2022Planning guest WC in new construction - How big should it be? (DIN?)107
27.12.2022Door DIN left or right – are both possible?17
20.09.2024New construction - Costs of plumbing & heating experiences?15
07.11.2024Is window planning mandatory according to DIN 5034-2021-08?13
20.11.2024Is staircase DIN 18065 mandatory or not?82
14.02.2025The planner does not perform any calculations according to DIN 27660

Oben