Where did it explode for you? Problems during house construction.

  • Erstellt am 2019-10-27 08:01:44

Climbee

2019-10-31 11:56:21
  • #1
With our general contractor (GU) we also had no difficulties at all and are very satisfied.

However, the tiler he subcontracted recently has an employee who does not work as precisely as he does himself. Unfortunately, we were the first for whom he laid tiles. The bathroom had to be redone and in my eyes it still isn’t really nice today. Strangely, he did a great job on the ground floor, where the tiles were even larger.
Our GU then had trouble with this employee at another construction site as well, and by now he completely refuses to work with him. Well, we just got unlucky that we caught him.

The biggest trouble we have is with the glazier, whom we hired ourselves but who was recommended to us by the GU. The work itself is okay, but he apparently has a lousy supplier for safety glass. All the glasses delivered so far are defective and this has been dragging on since early July. We will probably demand replacement of all glasses installed so far (and the defect is really so egregious that there is no need to debate it). This is quite annoying. I think the glazing company may have taken on a task beyond their capacity. We also received mirrors from them, about which we have no complaints at all, but whether we ever get our glass railing exactly the way we want it remains to be seen.
Here too it is very embarrassing for the GU that we took the glazier based on his recommendation, but oh well...

Plumbing: the installer from the GU crew told us: order the stuff yourselves on the internet, you get it cheaper there. We ordered in consultation with him and it worked out well for us.
 

MadameP

2019-11-01 15:26:28
  • #2
As if I had a premonition. Our plasterer (inside+outside) bailed. Was only supposed to start on Monday

Plasterer last week: blah so much to do stress can’t make it
Client: oh please
Site manager: we’ll manage, just send me the material and the people I’ll coordinate everything
Plasterer: hm don’t know
Site manager: think about it
Plasterer end of last week: alright then
Client: phew. Site manager = superhero
Site manager this week to client: maybe only the base plaster this year, weather and all, top plaster in spring
Client to general contractor: can we maybe move in without the top plaster and paint if we have to? Repayment start and all
GC to plasterer: whiny mouth
Plasterer: ok bye then

That was the short version, I think anyone currently building can relate.
All other plasterers in the area be like: no you’re booked up until August 2024.
End of the story: construction is at a standstill until a new plasterer is found. Everything else is pretty much ready, without interior plaster nothing else can continue for now. House connections, ring earth electrode, L-stones garden, foundation slab for tool shed - none of that can happen because the scaffolding is in the way. Paving & terraces not happening either because of course no base plaster.
I’m gonna go shoot myself now.
 

Lucrezia

2019-11-02 09:12:56
  • #3

Who did you build with, Yosan?
 

Yosan

2019-11-02 10:24:36
  • #4

We are building with Town & Country. I don't know how much leeway the individual franchisees have regarding the additional costs etc., but surely some... after all, the craftsmen's prices are not the same everywhere either.
 

KEVST

2019-11-02 11:11:10
  • #5


Until 2024?! Wow. Where are you building?
 

HilfeHilfe

2019-11-02 11:21:06
  • #6

I would raise prices
 

Similar topics
11.03.2018Optimization of Angle Bungalow 108 by Town & Country21
10.07.2019Town & Country - Rotex Heat Pump12
20.08.2018Town & Country Flair Floor Plan Changes24
11.03.2021Tiles first or plaster first12

Oben