Nida35a
2020-07-24 08:22:31
- #1
built 2 years ago in Berlin, rear property, 60m to the utility room,
1. Excavation for construction road
2. Excavation of media trench
3. Laying from property boundary to the height of the utility room
- Wastewater 100mm up to the predecessor, from there 125mm to the street, with 2 T-pieces as inspection points on the way
- Empty conduit water utility (blue) with pull cord
- Empty conduit telecom (gray HT) with pull cord)
- Electricity 5x50mm2 from power box to utility room + 10m reserve for connection
- Two 5x2.5mm2 cables and 8x0.8mm2 (path lighting, sockets, gate drive, video doorbell system)
- We do not have gas,
4. Close trench
5. Construct construction road up to 1m before the base slab
6. Electrician connected the cable to the gray box and construction power at the rear,
Construction water from the predecessor,
7. House construction
8. When the scaffolding was gone, open 2x1m at the utility room, 2x2m at the street, call water and telecom (if you don’t come now, you have to dig yourself), after 4 days everything was connected,
9. Move in via the construction road
10. Paving, terrace, garden, fencing system,
the fence was finished 8 weeks ago
Greetings Nida