What are the realistic costs for a semi-detached house / Kfw70 in Baden-Württemberg?

  • Erstellt am 2014-08-26 14:42:02

Wastl

2014-08-27 10:41:19
  • #1
We paid about 7000 for an average kitchen and another 4000 for electrical appliances. Garage: A metal garage including foundation is doable for 7000. A prefabricated garage measuring 3x6 meters with foundation is already around 10k € (those were the quoted prices for us). A masonry garage with an additional extension costs between 15 - 20k €. You see: Depending on quality and size, there are price ranges. I would also contractually ensure for the external development that additional costs must be paid by the developer,... We have already gone from the stated 70 € per sqm to 90 € per sqm development costs and it is still not finished,...
 

goblin

2014-08-27 11:07:03
  • #2
Hi construction expert,

thanks for the detailed reply.



The architect/site manager told us this number first. Since I wanted to know whether the architect's figures were realistic, I asked the city about the development costs. Here I received exactly the same information. That already gave me a positive impression.



What is included in that which is not already listed above?



What we see as a major advantage in the architect contract is that the ancillary acquisition costs are only about €6,000 instead of about €24,500. That’s a difference of €18,000 for which you ultimately get nothing. That is actually the main argument for us. However, the costs named and planned by the architect should of course be realistic.

Best regards Goblin
 

backbone23

2014-08-27 11:13:38
  • #3
In this forum, a topic "Baunebenkosten" is pinned at the very top of the list ...
 

Naddl

2014-08-27 11:19:09
  • #4
We have Siemens appliances and a Wellmann kitchen (Alno belongs to Wellmann, so the quality is the same. The difference lies only in the selection of cabinet heights and depths) and paid only 6500 euros all in. The appliances were bought separately but installed by the kitchen installer. If you look around a bit, you can get there (especially since you already have a few appliances!)
 

goblin

2014-08-27 11:46:53
  • #5
Hello,



Thank you for the hint, but I know this post. However, among other things, the following are listed here

- 5% real estate transfer tax - varies by municipality
- approx. 2% notary fees, calculated from the purchase price of the property
- approx. € 2,800-€ 3,200 surveying services (qualified site plans / height surveying / staking out / building surveying)

which have already been taken into account in my calculation. Therefore, I inquired again.

In our calculation, for example, surveying is already included in the engineering services, and this price for the engineering services would also be fixed. How do you actually assess this one block? Do you consider the engineering services for €38,500 including surveying, structural engineering, architecture, and construction management appropriate or too expensive?

Thank you very much
Best regards
Goblin
 

Bauexperte

2014-08-27 12:18:05
  • #6
Hello,


All the nice little things which add up to an ugly number and are often forgotten in the financing.


Please don’t be naive!

An architect contract simply means that on the one hand you have an architect who provides all the engineering necessary services and sends you an invoice for that. On the other hand, they carry out the tendering, check the incoming offers, and together with you commission the craftsmen according to VOB. If you book all service phases with them, they also take over construction management including documentation; of course, that costs money too.

BUT – you don’t actually save a real €24,500 on incidental costs, do you?!? These costs => for example sewer, gas, water, electricity, internal development, possibly additional foundation costs up to smaller bills for the chimney sweep or the application for a house number <= still arise AND you pay them!

By the way, I would like to clarify the terminology again here with precise explanations. If you were actually to conclude a real developer contract, you would also have to bear all these costs (they are included in the total price); but you would have nothing to do with tendering, nor would you have any choice, even to consider the exclusion of a trade! There would be a maximum of 7 payment steps, with the 1st being about 30% as the land portion must be paid for.

The example you describe is neither “fish nor fowl” – it lies somewhere in between and “can” go well, but it doesn’t “have to.” The risk would be too great for me as well.

Rhenish regards
 

Similar topics
08.04.2015Install a technical room in the garage? Is this possible?35
03.02.2014Cost estimate single-family house with garage11
30.07.2014Bungalow with 140 sqm and garage in the floor plan13
05.09.2014Floor plan design of a 170m² passive house with garage18
26.11.2014House orientation / House entrance and garage14
21.04.2015Is a floor plan with a garage feasible on the property?29
06.05.2015Draft single-family house with garage/carport - please provide evaluation22
11.06.2015Single-family house with a granny flat & garage14
23.07.2015House without garage and basement? Attic expansion? Lipoma?85
29.07.2015Floor plan of a single-family house with garage18
27.08.20152 full floors, passage to garage, utility room under stairs25
29.12.2015Single-family house floor plan / garage on the ground floor?10
15.08.2016Property - Building window - Location of house and garage44
18.10.2016Plan location of house & garage within building window *Pre-planning*129
29.11.2016Floor plans single-family house and garage32
30.01.2017Development costs and information before property viewing10
10.09.2017Floor plan, elongated single-family house, integrated garage, no basement16
18.05.2018Single-family house with >180 sqm / basement / garage68
25.06.2018Heat pump foundation too close to garage, repair or new construction?10
10.02.2020Place house, garage / carport on the property93