It doesn't quite fit the title, but since this is about the problems, I'll ask here:
The screed has now been poured, unfortunately the craftsmen were not given the current plan. The kitchen area and the building services room were poured at a height intended for tiling, so 8mm too low. It's not about a large area, maybe 18 sqm in total. The coverage of the heating is also sufficient, so it's about compensating the height difference now.
What would be a sensible approach here? Just put leveling compound on top or is that too simplistic?