Hello "Wintersonne".
Your question appears simple at first glance, but many aspects need to be considered behind it.
I will first answer your question from a simplified perspective.
There are conventionally installed screeds, i.e. wet screeds, based on cement as well as calcium sulfate. The latter was previously called "Anhydrite screed".
Such screeds are installed in residential construction with nominal thicknesses of 45mm and, under favorable drying conditions on site, dry in about 6 weeks until ready for covering. This rule applied to screed thicknesses up to 60 mm. For each additional centimeter, the calculation must be squared, so for example with 80 mm (thus 2 cm additional thickness) we would assume 6 weeks + (2 cm squared = 4 weeks).
Calcium sulfate flow screeds (abbreviation: CAF) dry faster due to the curing mechanism differing from cement screeds, so the readiness for covering can be expected earlier.
However, this does not mean that the readiness for covering has actually been reached. This can or must be confirmed by residual moisture measurement (the CM method is customary in the trade).
------------------
That was the simplified explanation.
Due to the demands of builders and planners for the shortest possible drying phase of the screeds, the industry has reacted and offered so-called "screed additives" that, among other things, are intended to shorten the waiting time until readiness for covering.
Some of these work, others do not.
The "crux" is, however, that all screeds with additives not only deviate from DIN standards and thus must all be considered special screeds (a legal aspect sometimes also looms threateningly in the background), but the properties of the screed mortars have also changed as a result. Among other things, such screeds can no longer be reliably measured by the CM method in every case (and thus the readiness for covering cannot be checked).
With the calcium sulfate flow screeds you mentioned, it has become even more complicated.
It is not found in any literature, but we experts in the field notice that due to recipe changes made by manufacturers, the pore sizes in the hardened flow screed have become smaller. Which has a considerable (unfavorable) effect on drying.
To cut a long story short: Even with heated screeds, where logically the thermal pressure would suggest a shortened release time of the mixing water – the opposite has happened, instead a prolongation of the waiting time occurred.
----------------------------------
This means: The readiness for covering can only be determined by CM measurements or by a DARR test (this is only carried out by experts, not by a craft business).
According to current standards, a drying time of 5-6 weeks can be expected for cement screeds with thicknesses up to 55 mm, and 7 days for CAF (not as heated screed).
Provided that appropriate room climate is maintained (shock ventilation and external heating in winter).
I hope these (somewhat more extensive) information have shed light on the matter!
Regards: KlaRa