tumaa
2021-04-08 09:29:14
- #1
He is no good for it, he can't do it I had already paid... 50 rolls just for the screed? It felt like for the screed for the ground floor, upper floor, and attic = I would maybe estimate 1800mIt's really crap to have such disputes. Basically, the electrician has to calculate his time and include it in the offer. If he miscalculates, that's only your problem if it arises from constant changes or extremely high communication needs. I would proceed as follows:[*]Determine what is missing. [*]Withhold the amount for it + risk surcharge [*]Have it completed [*]Material price increases and pipe meters are not clearly identifiable to me, but also not so relevant in total. [*]Settle the invoice as last requested - with 100% functionality. [*]oh yes - and even if it's tempting: no remarks on the individual interpretation of the spelling - it just adds fuel to the fire.
That way you get the desired result and have the shortest time of trouble. Maybe not financially optimized by all rules of the art, but optimized for quality of life.