Massive house company sought in the Waiblingen/Rems-Murr district area

  • Erstellt am 2020-09-16 18:24:05

Evelyn!

2020-09-16 18:24:05
  • #1
Hello, my construction project experienced significant delays of over a year due to the architect and the city, and now the originally chosen construction company has raised prices considerably even though the house has become smaller after a redesign. Therefore, I would now like to obtain comparative offers for the existing plan (which has already been approved). It is to be a solid house with 2.5 floors and a granny flat. KfW55 or better KfW40plus, as a photovoltaic system is mandatory for me. The construction method should do without additional external styrofoam insulation. Can anyone recommend a company to me? Some time ago, I inquired with many companies but in the end only a small fraction even responded, and from an even smaller portion, an offer eventually came. Can anyone recommend a company that builds in Waiblingen? Would be grateful for tips
 

Baufie

2020-09-17 08:35:07
  • #2
Do you only need a shell construction or should it be turnkey?
 

Evelyn!

2020-09-17 10:07:34
  • #3

It should largely be turnkey with the option to perform some work myself. For example, I might be able to do the floors or tiles myself. The rest should be taken care of by the company. So a general contractor or main contractor.
 

K1300S

2020-09-17 10:28:03
  • #4
I thought you have an architect. Then it would be (only) a generalCONTRACTOR.
 

Evelyn!

2020-09-17 12:16:54
  • #5
The architect only finished the building application, I don't want to build with him, that part was exhausting enough...
 

11ant

2020-09-17 16:54:59
  • #6
There is a moderated section here on the topic of experiences with construction company XYZ. If you enter Waiblingen or Rems / Murr or not too tiny neighboring towns in the forum search (or also possible candidates right away, if you already have some in mind and want to read assessments about them), you should be able to find something.
 

Similar topics
19.07.2018Draw the plan yourself? Do you necessarily need an architect?11
18.02.2011Architect totally messed up - experiences?17
30.09.2012Final invoice architect13
27.10.2013Architect --> Agreements? What is that?21
16.04.2014Cost of soil survey - Does the architect pay or do we?12
16.09.2014Termination of collaboration with architect - demands excessive fee28
25.08.2014Architect / Contractor: How to best approach the matter?15
01.10.2014Collaboration with an architect - how does it work properly?22
11.11.2014The Old Suffering - Turnkey/Individual Contract38
25.02.2015Planning / Architect, involvement of specialist planners for the approval plan10
10.04.2015Cost estimate architect single-family house. Your assessment44
26.04.2015Semi-detached house architect or general contractor / prefabricated house or solid construction13
27.12.2015Who has built with an architect? Experiences??85
11.09.2015Building a garage on the boundary is not possible according to the architect.11
17.11.2015Is an architect really that expensive?46
05.04.2020Developer or architect - costs43
07.03.2016Various dimensions architect execution drawing12
23.09.2016Architect and budget limit... insurance? possibilities25
17.11.2019General contractor in the Munich area or prefabricated house?37
24.02.2025Construction Costs Shell/Turnkey Comparison39