nordanney
2024-02-29 18:54:25
- #1
What special finishing? It’s supposed to be only the usual things like painting/sanding, laying floors or other small stuff. That won’t take months. Realistically, you don’t need more than a few days off and the weekends.How many working hours have you actually planned for the interior finishing and in what time period do you want to accomplish that? In the meantime, you are paying rent or living on a construction site. And even if 35 hours is not much: if you don't live very close to the construction site, realistically only the weekends remain mostly for the finishing.