Acof1978
2021-05-10 13:25:02
- #1
Ultimately, the main contractor does not agree on fixed prices with the individual trades. The price increase is simply passed on from the carpenter to the main contractor. Since the two companies want to continue working together in the future, it is usually split 50/50 or similar, depending on how "lenient" the main contractor or the carpenter is in that case.
In the end, the main contractor currently has less margin on all the houses—period. As I said, unless there is a clause in the contract, I would not pay an extra €2,500 or similar—why would I? Then the main contractor simply earns less on my house. He will have to calculate his future offers more sharply to recoup the lower profit on the current construction projects.
Entrepreneurial risk....
Not always. Our main contractor fixes the prices with his regular suppliers after the client’s approval. For example, we gave our approval in October 2020. The building application was submitted in December. Due to the conversion of the plot and the "quick" processing by the forestry authority, construction will only start at the end of July or August 2021. The main contractor confirmed again last week that the prices will remain valid until the house is completed.