So far, he has only hinted at it as a side note. The bigger problem he described was primarily about procurement and incidentally mentioned how we could then solve it financially since no one could have anticipated it. If you Google it, it seems that currently there really is a very tricky situation on the German market.
I have another suggestion. You can accept part of the additional costs, but never without consideration. For example, one would then negotiate and contractually fix a delivery date guarantee and/or payment only after defect-free acceptance.