um, the price fixing should generally relate to the start of construction. In other words, when the general contractor (GU) begins, he has to complete the house within period X at price Y. If he delays the construction, he has to pay penalties and not charge additional costs. With the contractor's argument, he could also delay the installation of the doorbell for 10 years and then demand the house price from you 10 years later. (Yes, this is exaggerated, but that’s what it comes down to.)
But the contract structure must be very strange, you apparently have already been to a lawyer and even he advises you to pay 15-20 k€?!?
Maybe you can provide a bit more information, as this doesn’t add up.