What kind of insulation is behind your clinker bricks?
The wall structure is described as follows:
43cm cavity wall, consisting of:
- 17.5cm aerated concrete block
- 12cm insulation 035
- 2cm air gap
- 11.5cm facing brick
I hope you haven’t paid too much yet in % of the total amount.
So far we have paid
- 2.38% for architect and other services (after receiving the building permit)
- 10% after completion of the base slab
The next installment would be 25% once the floor slab is in place
Is the ceiling possibly being waited on because its production has not yet been scheduled due to payment reasons?
They probably won’t tell us that, but the suspicion is obvious. Allegedly, they are handling 4 construction sites simultaneously for our developer, I overheard that between the lines...
We also suspect the "fire brigade" and a few skilled workers. On average there were always two people there – how good they were at their trade is apparently visible...
Our site manager was rarely reachable and we always had the impression that he did not know what was actually happening on our site or what should be planned next...
We met him 3 times and twice he didn’t know, for example, that we also wanted to do some work ourselves...