Evaluation of Construction Project / Credit Offer

  • Erstellt am 2020-01-10 18:15:42

kbt09

2020-01-12 15:06:25
  • #1


Does this fit with my generous calculation:
2 persons * 2 periods * 3 weeks * 50 hrs/week = 600 hrs plus an estimated additional 600 hrs over time plus helper hours ==> total of 1200 hours of personal contribution, which is already a very generous estimate.

Since it is usually said that 2 "layman" helper hours replace about 1 craftsman hour, that would be

    [*]€40,000 / 600 hrs an approach of 600 craftsman hours saved at €66/hr each
    [*]the remaining €60,000 equity capital is presumably brought in as items etc., apparently what the bank recognizes .. or how? And where does the money for the materials come from?

I think this needs to be laid out more precisely again. To me, it certainly does not seem plausible as it is.
 

BauherrSaarlan

2020-01-12 15:18:35
  • #2


We have broken down the own work as follows:

- 20,000 euros for: laying floor coverings (tiles), working on walls, wallpapering, painting, as well as installing interior doors
- 10,000 euros for landscaping (driveway, paths, terrace, garden)

The 2x 600 hours shown above would be for the first area, i.e. for own work worth 20,000 euros.

The remaining 10,000 euros (landscaping) we will carry out in a later period and do not want to put any time pressure on ourselves for this; if it takes longer, so be it.

In addition, we are bringing 30,000 euros cash as equity capital = a total of 60,000 euros, where we anticipate few problems regarding bank recognition.

According to information from a prefabricated house seller, 30,000 euros instead of 20,000 euros would also be possible for the first block, which is usually recognized by banks; then the total equity capital would be 70,000 euros.

The rest will not be recognized by banks, so for example, in the meantime, we will still save money and invest this in the landscaping (provided it is not needed elsewhere for the house construction).
Additionally, we are contributing a very expensive grill hut, which currently stands at another location but will be moved; the pure material price of the wood and especially the grill equipment was around 15,000 euros three years ago.
 

matte

2020-01-12 15:38:37
  • #3
Sorry, but now it’s getting strange. A barbecue hut as equity...
 

BauherrSaarlan

2020-01-12 15:42:20
  • #4


Now it really gets bizarre... It clearly states that this of course is not recognized by any bank, but by definition it is nothing other than equity. We want a barbecue hut, it already exists, so these costs do not arise in our project. Not decisive for the financing itself, but since the question came up about what "items" we contribute, it was mentioned (and it is clearly distinguished as deductible equity).
 

kbt09

2020-01-12 15:43:36
  • #5
Financing requirement: 500,000 Euros

Item: 100,000 Euros for land
Item: 400,000 Euros for house and all possible ancillary services:



Have you ever read ? Attention: Please note that the data are partly up to 6 years old, i.e., the type of cost still exists, but the costs have often increased considerably. See also recently on Spiegel-Online. This has also been reported here in the forum several times, namely rising costs for excavation/removal. Or according to soil report then often rising costs for the floor slab, which is only included in the house price up to a certain excavation depth and after that subject to extra charges.

Also connection costs ... Municipality is one thing, but what about electricity, communication service providers etc., that is usually not covered by the municipality.

Kitchen is actually not something that belongs in the usual financing.

And what is always gladly forgotten in self-performance, you need the appropriate equipment and the right tools.

For floors, often only the price per sqm is looked at, you also need skirting boards, separating strips, adhesive material, etc.
 

BauherrSaarlan

2020-01-12 15:50:28
  • #6
Yes, I have already read this through. I think the additional construction costs are estimated relatively generously in our case but were not listed completely above, only exemplarily. Connection costs: Here we already have very concrete figures, included are: water, wastewater, electricity, telecom, cable connection (but probably only telecom or cable connection besides, still included both for now). Despite everything, we have included the kitchen with 25,000 euros. Suitable tools are fully available. For the floors, we assumed €50 per sqm; in the current preliminary selection, no flooring (we will use almost exclusively tiles) costs more than €40 per sqm, on average it’s about €35. The higher calculation takes into account waste/leftover material and all additional costs such as baseboards, adhesive material, etc.
 

Similar topics
01.05.2013No equity / existing consumer loans / financing possible?11
07.10.2014Renounce Telekom connection30
01.01.2016Cost of house connection for Kabel Deutschland and Telekom?37
30.05.2016Apply for Telekom / Unity Media connection in parallel11
16.07.2016Telekom connection - line already laid, still have to pay 600€?29
08.08.2016Connection costs for telecom, cable, electricity10
01.02.2017Duration of completion notification for Telekom house connection22
14.01.2018Kabel Deutschland or Telekom or both14
10.01.2018Telekom says TV is not possible - Can that really be true?29
20.02.2018Telekom home connection, your experiences. Is Magenta M okay?43
06.11.2018House connection: Telekom does not want to drill through the white tank17
05.12.2018Dispute between telecom and municipal utilities - house connection10
11.04.2021Plan a conduit for Telekom?21
12.11.2020Internet connection: Deutsche Telekom vs. cable network33
30.03.2020Telekom FTTH - What is needed?30
03.01.2021Problems with Telekom. Crossed cable?33
19.02.2021Telekom Hybrid or Vodafone Cable - Advantages & Disadvantages for Internet36
04.01.2022Cable vs. Telecom Fiber Optic - Decision56
02.12.2022Creation of the house connection by Telekom15
11.03.2023Fiber optic expansion by 1&1 or Telekom - Who pays for the construction trenches?20

Oben