Construction company price increase of 25% – Expired fixed price guarantee

  • Erstellt am 2022-05-17 17:24:16

WilderSueden

2022-05-22 10:34:34
  • #1
That has to be decided by the original poster. The statement was that a 25% surcharge would no longer be bearable. In addition, he has the problem that he is still far from the building permit and therefore would have little security even with a new commitment at X%. Since the alternatives currently also look rather bad, this would probably result in a termination. However, the quoted part was mainly about the question of the 10% contractual penalty which should be significantly mitigated by §313.
 

MarkoW.

2022-05-22 11:48:09
  • #2
Doesn't a consumer contract (one of my former lecturers at university once said that the consumer is treated by law like a "stupid piece of wood") have to explicitly state which price increase applies after the fixed price period expires?

For example, ours states that we must meet the builder-side delivery requirements within 10 months (building application, developed plot of land, etc.). Unfortunately, we did not manage to do so, so since the 11th month after signing the contract, the house has become 0.4% more expensive of the order value. However, this was clearly communicated in the contract from the beginning. Not nice, but still bearable and far from the 25% discussed here.
 

11ant

2022-05-22 12:44:27
  • #3
It works rather poorly, because this "theory" would already be the wrong conclusion. It must be correctly said: "as late as necessary." You have to "apply pressure" during the "homework phase," that is, when the conditions for the signature are being created - not when signing itself.
 

Tassimat

2022-05-22 13:52:55
  • #4

Maybe I overlooked it, but how far away is the building permit still, in the worst case?
 

WilderSueden

2022-05-22 15:06:39
  • #5
Worst case is not mentioned, but the best case doesn’t sound very promising either. So we’re basically talking about half a year until approval. My guess is that the application hasn’t even been submitted yet, in which case it could take even longer.
 

Similar topics
31.10.2008Is a building permit also required for a carport and equipment shed?13
15.02.2011Building permit application12
27.09.2018Cost of building permit in exemption procedure, new construction11
28.11.2024Neighbor's lawsuit against approved building permit46
16.01.2017No building permit as long as the land is not developed?10
20.08.2017Issuance of the building permit?24
08.01.2018According to the law, the building permit is automatically granted if12
21.06.2018What must be included in the building permit? Legal certainty?19
18.09.2018Immission protection concerns self-service gas station - building permit?20
24.10.2018Broker sells house without current building permit. Notary costs?25
28.08.2019Building permit for terrace roofing14
04.11.2019Is only part of the building permit enforceable? How long is the building permit valid?42
10.01.2020Construction loan without building permit possible?17
23.09.2020Child construction allowance with non-final building permit49
30.07.2021Is building without a building permit possible?26
17.11.2021Official liability building permit neighbor - keywords sought14
28.06.2024Building permit - is a lawyer useful?12

Oben