Collection and landfill costs

  • Erstellt am 2011-11-28 13:09:58

Bauexperte

2012-04-25 16:38:22
  • #1
Hello,

You dare to do something and in my opinion are also a bit naive


I do not know where you get your knowledge from – the fact is that only the group of low-cost providers, specifically their subcontractors – here the earthworks contractors – must take this path. Houses are – against better knowledge – increasingly offered at lower prices; mostly at the expense of the executing craftsmen; however, the margin remains largely untouched in the house of the original provider. To achieve a somewhat acceptable result, these craftsmen are forced to make their margin through after-sales. This is exactly as most nationwide operating providers want it. On the one hand, it saves their salespeople the difficult price negotiation, on the other hand, for the above reasons, the craftsman must take on this part. The providers always come out fine, and the subcontractors get the blame for it as a thank you.

However, it is up to each builder – at least in the earthworks trade – to obtain further offers for comparison. Therefore, I do not understand – at least in this point – where the problem should be.

Kind regards
 

Häuslebauer40

2012-04-25 23:09:13
  • #2
Construction expert, it may be that I have not understood your explanations correctly, but that may also be beside the point.

For me, one thing is certain: if a company charges a customer for removal and landfill fees for the disposal of excavated soil, but does not dispose of the soil and instead resells it as fill material to the next party, then that is double charging and anything but correct.
If the material is reused on another construction site, the company should in fact pay the client from whom it received the material a compensation, or at least only charge for removal and not also for a disposal that does not take place.

Where do I get my knowledge from? Well, from whom else? From civil engineers whom I know personally very well.
 

Bauexperte

2012-04-25 23:31:37
  • #3
Hello,

Then ask them where they apply this tactic and where not. And you surely have told them your opinion. Nevertheless, this does not change the fact that you absolutely cannot make this statement in general.

Kind regards
 

Häuslebauer40

2012-04-26 09:51:34
  • #4
Hello construction expert,

of course, you can't just lump everyone together. Where do you apply this tactic? Everywhere where clients are satisfied with insufficient evidence.
By the way, the BU also tried it with me. With handwritten delivery notes on which estimated tonnages were noted. But I simply don't accept that... either proper weigh slips from the respective soil depot or send the invoice to dear God...
 

Hilaria

2012-04-27 08:38:16
  • #5
So, I do not want to deform anyone here. Nor do I assume that everything is running correctly.

As a layman, I am confused; I was given cost estimates based on sqm, how is this correctly billed?

Furthermore, in my contract with the BU, the excavation itself is already included, but since there is no storage possibility on the property (how much space does one approximately need for an excavation of around 400 sqm?), it must be transported, deposited, and brought back again.
Now it is about these things, i.e. parking the truck, (loading is practically already "paid for"), removal... (refilling is also already "paid for"), only the delivery is not.

Hilaria
 

Bauexperte

2012-04-27 11:59:51
  • #6
Hello,


You also shouldn't feel addressed


By cubic meter; length x width x height of the excavation pit, plus allowance for the working space and depending on the necessity for the slope angle.


Probably no more than 2 to 2.5 m for the earth mound; deep foundation workers are not fine technicians. For 400 cubic meters, it would require about 20 x 20 m of space.

Best regards
 

Similar topics
11.07.2011Basement costs realistically without excavation and removal?21
27.08.2015Temporary storage of excavation from the neighbor's property?22
15.08.2016Civil engineer contradicts structural engineer27
12.07.2017Excavation of construction pit - analysis of excavation material?12
02.10.2018Excavation for the basement, your opinion on the cubic meters31
02.04.2019Building plot: Massive fill or better basement with excavation?28
08.04.2019Waste removal, disposal, earth excavation Werneuchen BB12
04.06.2020Civil engineer proposes deviations from the drainage plan10
14.09.2021Civil engineer calculates excavator performance by tons - experiences?21
08.08.2022Costs for basement excavation without disposal21
22.11.2022Rough staking changed, excavation incorrect11
09.01.2024Assessment of an offer for earthworks22

Oben