xMisterDx
2024-01-08 22:16:33
- #1
700t of gravel fit well with 400 cubic meters of excavation. I think there is a certain slope here that is now being balanced out with a large amount of gravel. 35€ net per ton of gravel is quite a steep price, the gravel pit probably charges only half of that with delivery free to the construction site.
500 cubic meters of topsoil seems a bit much to me. We're talking about roughly 1500sqm of area to be worked on.
Deliver, lay, and compact gravel.
Sure, the gravel pit unloads 30 truckloads there. And then?
Do you know the size of the property? Why should 1,500m² be unrealistic?