Building acceptance of new construction despite missing heat pump. Significant defects?

  • Erstellt am 2022-09-18 17:35:42

HessamA

2022-09-18 23:57:00
  • #1
Thanks for the effort you are putting in. I really appreciate that.

So what I have taken away now is that I first find out what alternative he offers here. I did not know about the mobile heat pumps. In my ignorance, I assumed a solution like electric heaters and instantaneous water heaters, which thankfully would be nonsense. Is a simple phone call enough here, or do I need the solution in writing to have something conclusive?
 

11ant

2022-09-19 02:14:36
  • #2
I, too, would have recommended as appropriate to carry out an acceptance with defect protocol – if the word "if" were not there (and the developer behaved professionally accordingly), but unfortunately you probably have to ask him to do so first. An operational and permanent heating system not delivered at the agreed time – that is, not yet at the acceptance date – is in my opinion only provisionally adequate to the agreed delivery if the developer makes a concrete statement in good time before the date on the following points: a. technical concept of the interim solution and its expected duration; b. his willingness to accommodate higher operating costs of the interim solution and, if applicable, "compensation" for the more complicated operation thereof; c. handling of overruns of the anticipated interim solution phase. So far, he has not considered any of this necessary, although he (hopefully!) has not been building residential buildings commercially for "consumers" only since yesterday! So far, the OP must fear that the interim solution might consist of "wear three jackets on top of each other" and/or "keep yourself warm by thinking warm thoughts" and last until doomsday or at least until "we’ll see when." However, this is, in my opinion, to be decisively rejected as an outrage. I could imagine that following my suggested approach (which, mind you, includes no threats of overreactions), the OP would end up "like nothing the world has ever seen" in first place on the developer’s heat pump waiting list. Whoever barks back the quietest draws the short straw. You are indeed ignorant – but mostly because your contractual partner has not clearly stated anything so far. This solution path would only be nonsense in theory – the fact that so far no one dares to try it in practice is not guaranteed. You don’t mean that question seriously. You always "talk" to sly foxes in writing, better one registered letter too many than one too few.
 

allstar83

2022-09-19 09:05:26
  • #3
Possibly bring in a building surveyor for the inspection? They could then be the scapegoat depending on your interests...
 

K a t j a

2022-09-19 09:46:01
  • #4
As a rule, written form is recommended for major defects, even if the BU is the dearest friend ever. I wouldn’t accuse slyness here yet. Everyone has probably noticed by now that technology is becoming scarce. The BU is also not guilty of the defect fraudulently – I’d rather ring Mr. Habeck’s doorbell for that. That he needs an acceptance is obvious. He can’t leave all projects as unfinished in the books until doomsday, otherwise he would have to file for insolvency tomorrow. The big question remains: what does he offer as an alternative? Here I would try to find a joint solution in conversation. If nothing or little comes of it – lawyer.
 

allstar83

2022-09-19 10:48:30
  • #5
One more thing. We did an interim inspection before moving in (the carport was still missing, etc.) No idea if that's legally sound. However, during the time until the final inspection, you could test the whole house and certainly noticed one thing or another.
 

HessamA

2022-09-19 11:11:38
  • #6
Hello dear all,

I had a longer phone call with the developer today. He told me that there is currently an electric heating system in the house that heats the entire house. This is necessary because of the screed and would heat the entire house. He would cover the costs for the electric heating without any objections for the duration of the provisional arrangement. He also assured that we will have hot water on the day of acceptance. He will inform me exactly how that will be. Since there will be additional costs due to the provisional arrangement, he will fully cover all of them. We will also record this in writing in the acceptance protocol. He also offered me to withhold the security deposit, which is stipulated at 5% in the broker and developer contract, with the argument of incomplete completion. That would be okay for him.

When I asked him if he could confirm what we discussed in writing, he denied it, arguing that all of this is contractually agreed upon and does not require a separate written confirmation. And that we would fix the issue with the heat pump in writing at the acceptance appointment. However, we will not be able to enter a deadline here because the supplier - the company Vaillant - currently cannot give a date and does not provide any information.

What is your opinion on this?
 

Similar topics
06.02.2013Developer says: No more insulation!12
23.03.2011Developer or architect?15
09.07.2012Developer offer for single-family house - Are the construction costs acceptable?16
16.07.2012The builder "outsources" fixed-price services to subcontractors12
30.09.2012Developer - Is withdrawal from the purchase contract possible?11
01.12.2014Real estate transfer tax / what is the tax applied to? Which developer MUST?30
18.02.2014Massive problems with the builder - is contract termination possible?33
23.06.2014Developer charges heavily for replanning - justified?12
08.10.2014How do you search for a suitable property developer?30
27.02.2015Construction project with a developer without an official building plan, is a down payment required?12
01.03.2015The developer does not build according to the plan14
15.04.2015Duplex construction: Joint or separate developer?20
13.06.2015New construction with developer / construction drawing documents23
09.09.2015Buy land separately from the developer13
24.12.2015Single-family house, Energy Saving Ordinance 2016, developer recommends additional insulation - is it sensible?39
15.03.2016Developer changes plot size25
16.03.2016Single-family house - developer rejected25
12.11.2017Exchange old night storage heater for modern electric heating16
09.06.2020False statement by sales partner at developer12
31.05.2021House with electric heating and built-in open fireplace17

Oben