Building acceptance of new construction despite missing heat pump. Significant defects?

  • Erstellt am 2022-09-18 17:35:42

SaniererNRW123

2022-09-19 11:16:13
  • #1
I find it conclusive. The topic of WP and costs for the electric heating should be documented in writing. Everything else can actually no longer be put into writing, but feel free to draft a letter yourself. In essence, "I am happy to summarize our conversation as follows..."
 

WilderSueden

2022-09-19 11:18:57
  • #2

I find it fair and reasonable. As far as I understand, you don’t suffer any disadvantage either. I would definitely withhold the last 5% until everything is in order. I would also absolutely summarize the conversation and send it again, as this makes it harder for the BT to deny the telephone agreements later.
 

11ant

2022-09-19 13:40:44
  • #3
Although the developer has formally made a written notification to the OP, it is no better in quality than an oral one, essentially something like: "Listen, I’m coming to the appointment with more or less empty hands, but please still have the money with you as agreed." That is called cunningness, insofar and because it hardly escaped him that he had not specified the "provisional solution" in terms of quality and duration, yet still relies on the OP’s unmitigated kindness. That they do not occupy themselves with daily tweeting their oracle about when things will finally progress further as part of resolving the delays is indeed a completely credible statement. When a ship is blocking a channel that is of global economic significance, chips don’t arrive on time. You can’t make that many extra shifts so that production would have fully caught up a few weeks after the blockage is removed. Whether water pumps require Ukrainian wheat, I don’t know. Speculating in real time about when everything will be "normal" again would certainly not be productive. However, what is important for you: the promise to cover the extra costs must have the same (possibly then not limited) duration as the waiting time still to be endured. Insisting that this be put in writing is absolutely appropriate.
 

HessamA

2022-09-19 15:45:47
  • #4
So once again, thanks to all participants at this point. This forum is a blessing and the exchange with you has helped me a lot.

I have decided on the following approach. I will write an email with the discussed contents and will carry out the acceptance with the help of a building expert. If I explain the situation to the expert in advance, he will give me his opinion on it. During the acceptance, he will look at the temporary measures on site and then tell me whether I can accept it as is or whether there is a significant defect or not. If he considers the temporary measure acceptable for occupancy readiness, I will – as discussed – document the missing heat pump as a defect in the report and further state that the developer will fully cover the heating costs until the delivery of the heat pump.

Regarding the payment: the contract states that occupancy readiness must be achieved by 30.09.2022 and the construction project including the outdoor facilities must be fully completed by 30.11.2022. The 5% security payment agreed upon in the contract will be withheld until completion. Until then, the developer can still carry out all work within the deadline.

Is that okay?
Best regards
 

HessamA

2022-09-28 16:41:49
  • #5
Hello dear all,

I have an update for you and would again appreciate your opinion/feedback. Today we carried out the acceptance accompanied by an expert. We documented 60 various defects in the acceptance protocol. Among other things, the heat pump - which was clear beforehand - was not present. The promised provisional solution in the form of electric heating and instantaneous water heater was on site (the devices themselves), but not connected. It was only said that the responsible electrician had suddenly become ill and that this work would be completed shortly. So, at the acceptance, we could not check whether we have electricity, hot water, and heating. Therefore, we also could not, for example, test the electric shutters, the underfloor heating, etc. After consulting with my expert, we concluded that the property is not ready for occupancy. We informed the developer of this and further told him that due to the many defects and the inability to check hot water, electricity, and heating, we refuse acceptance. He is of the opinion that the house is ready for occupancy. He then said that the acceptance is therefore finished and that he must proceed to the next acceptance appointment (there are three terraced houses). We did not sign anything.

What do you think?
 

allstar83

2022-09-28 17:22:53
  • #6
Did the developer countersign the report? I think you should formally hand it over with a deadline. Then it’s his turn again. You can do this politely but firmly and stay in contact. But 60 defects does sound like a lot.
 

Similar topics
01.03.2015The developer does not build according to the plan14
08.10.2015KfW70 only with heat pump now?26
26.10.2015Have the house inspected by a professional / expert?12
15.03.2016Developer changes plot size25
12.11.2017Exchange old night storage heater for modern electric heating16
28.05.2018Air-water heat pump or gas + controlled residential ventilation in a 135 sqm single-family house?19
10.08.2018Landscaping company - defects, high bill, no warranty?!13
14.09.2018Heating (Heat Pump) Incorrect, heat output too high?14
30.08.2019Is it sensible to have a building surveyor for condominiums from the developer?11
18.10.2018Liability for various defects after acceptance of the property19
15.09.2019Developer refuses to hand over documents32
09.06.2020False statement by sales partner at developer12
29.07.2020How to secure like ETW from the property developer24
13.09.2020BAFA funding for heat pump (air-to-water heat pump) when building with a developer25
09.03.2021Withholding payment for defects in the shell construction74
20.08.2022Heat pump not available, house construction stalled16
02.03.2023Heat pump for KfW55 house 148 sqm99
06.04.2023Deficiencies in the new construction. Dispute over the amount of withholdings.35
23.12.2023Broken tiles warranty? New apartment from the developer13

Oben