Turnkey fixed price during Corona or cost increase?

  • Erstellt am 2021-04-17 12:30:08

kati1337

2021-04-26 09:59:14
  • #1

Did you not have a fixed contract with the architect / general contractor before? Or are you awarding contracts individually?
Is there still a possibility to switch the executing company/companies?
30% sounds really VERY much. Before I would finance so much extra, I would consider whether I can do without something in the house? Or can you still easily afford the installment with 170k more?
 

michelsp

2021-04-26 12:58:04
  • #2
We have an architect contract that does not set a fixed price on the trades, only provides a rough cost estimate. We will then also award everything individually. He increased our cost estimate by 30% because in another construction project, for which he received and evaluated all the prices last week, that was the final result. According to him, our houses are comparable. We will also send the award documents ourselves to other companies; unfortunately, our architect makes it easy for himself and only asks his buddies, with whom he has been working for over 20 years.

We are already almost at the limit with financing, would then push it to the max, and are lucky that the difference could be received from the parents as an early inheritance. We also don't want to give up on as much as possible, and as couch potatoes, we don't dare to do any own work (except painting) :(
 

Similar topics
09.04.2013New single-family house including carport and garage - realistic cost estimate?11
21.07.2013Cost estimates from two architects differ greatly!10
18.10.2013Cost estimate single-family house Munich 200 sqm12
03.02.2014Cost estimate single-family house with garage11
28.04.2014Cost estimate - contract for work16
27.03.2017Cost estimate for a single-family house in the Munich area12
22.09.2017Prefabricated house cost estimation24
27.03.2018Questions about cost estimation per m3 FFM Hanau region14
22.05.2018Cost estimate for a single-family house near Heidelberg45
18.10.2018Construction costs for terraces, etc. in cost estimation according to DIN 2719
22.01.2022Check cost estimate from preliminary draft35
14.05.2022Cost estimation for building an architect-designed house - Munich surrounding area51
03.11.2023Cost estimation for an extension to a new building13
10.05.2024Architect cost estimation experiences?36

Oben