Gerddieter
2025-04-17 12:20:00
- #1
No, the plans are the contractual basis. The inconsistency of the masses only makes it worse for the contractor, not for the consumer. And seriously, these are not additional costs for the contractor. 8 sqm more floor slab - 500 8 sqm more screed - 200 Heating - he doesn’t add a single loop more because every room is a few cm wider. Parquet: you can offer to take over.