Is preparing for photovoltaics in new construction sensible?

  • Erstellt am 2021-03-15 12:39:00

GSGaucho

2021-03-21 19:35:28
  • #1
If you are still in the planning phase, I recommend planning a media shaft of about 20 x 40 cm from the attic to the basement or technical room. That’s how I did it. Accessible behind a cladding on each floor. Whatever may come.
 

Yaso2.0

2021-03-23 18:36:39
  • #2
After I read this thread here, I spontaneously said on Friday during the electrical sample inspection that we would like to have the preparation for photovoltaic offered.

The offer now states:

1 pc.
Preparation for photovoltaic system (connections from house connection to attic without connections of the cables)
Empty conduit DN32 110 €

Extend the meter cabinet by one distribution field to be able to accommodate more components of the electrical installation
450 €

Is that sufficient?
 

knalltüte

2021-03-23 19:28:47
  • #3
No! DN32 is (clearly) too small! At least DN50.
 

Yaso2.0

2021-03-23 19:50:22
  • #4
Silly question, but how does he then come up with DN32, he has seen the house plans.. And then only 1 x DN50 or do there have to be several:oops:
 

GSGaucho

2021-03-23 20:12:13
  • #5
I have around 21kWp on the house roof with 4 strings. Then there are 4 x each DC and control cables as well as one or two grounding cables. So I have about 5 empty conduits DN32 there.
 

Yaso2.0

2021-03-23 21:59:27
  • #6


Mine was pretty much very spontaneous after I read the thread here, I wouldn't have thought of it before..

Does it depend, for example, on the house size or orientation? Maybe I should familiarize myself with the requirements beforehand..

Who advises you in such a case? And do I basically have to set up some device later or something? I wouldn't have any space for that..
 

Similar topics
05.03.2010Passive house, heating combination with solar, energy recovery, photovoltaics?38
22.12.2015Is natural stone heating in combination with a photovoltaic system reasonable?16
09.04.2013Is financing a photovoltaic system unprofitable?11
08.12.2014Small photovoltaic system 2 KWp11
12.02.2015Photovoltaic systems & storage systems *collective thread*21
05.06.2015Photovoltaic system for hot water preparation and feed-in15
06.08.2015Photovoltaics for hot water26
20.11.2015Solar / Photovoltaic from an economic perspective53
08.01.2016Photovoltaic system: Self-consumption rate with battery and further questions27
23.02.2016Photovoltaic + Battery - Which System - Experiences?17
08.06.2017Photovoltaic system, how to use experiences like heat pumps?64
26.04.201616.03.16: Start of photovoltaic assembly60
16.07.2016KfW 40+ and 10,000 Houses Program - Requirements for Photovoltaics?13
06.04.2016Financing for 15 or 20 years? Photovoltaics via KFW?10
30.05.2016KfW55: Gas or air-water heat pump with/without photovoltaics17
30.05.2016Photovoltaics on the roof as a second layer11
21.06.2016Heat pump with photovoltaics vs gas and solar thermal52
10.07.2016Air-water heat pump with photovoltaics or pellet with solar25
13.07.2016Photovoltaic storage - experiences? Tips?17
10.10.2017New photovoltaic system with storage in single-family home - experiences39

Oben