Hello,
Of course, the costs for those "extras" that arise during the sample selection would still be added?! Getting out of there with "nothing" is rather illusory ...
I haven't looked closely at what you posted here in the first post – just so you know.
On the one hand – as €uro rightly pointed out – a reasonable assessment cannot be made just like that, on the other hand, the entire contract documents (floor plans, BB, cadastral extract, construction contract including payment plan) would have to be available. Something like this takes a good 4 to 5 hours, depending on the scope of the documents. What caught my eye at first glance is that – except for the heating system – no brand names are mentioned and also the pricing/series of sanitary objects are missing as well as the material prices for, for example, the tiles. I also find it funny – by the way, this is how most providers handle it – that the Ug-value for the glass is specified, but not the value for the frame and glass.
Topic additional construction costs ....
1. Land
5% property transfer tax – varies by municipality
possibly broker fees, about 3.5% of the purchase price, varies by municipality
about 1.5% notary costs, calculated from the purchase price
3 x registration in the land register (1. priority notice of conveyance, 2. transfer of ownership, 3. registration of the mortgage)
2. Financing
Possibly advisory/concluding costs for financing, about 1.5% of the total loan amount
About 0.25% commitment interest, calculated on the loan amount
3. Construction preparation
About €2,800–€3,200 surveying services (qualified site plans / height measurement / staking out / surveying the building)
Creation of soil report, about €1,200
Provision of connections for construction water / construction electricity, about €6–€8 rent for standpipe/day, about €300 rent for construction electricity meter
Fees (for house number, drainage permit, building permit), about €1,000–€1,500, varies by municipality
Fire/construction liability insurance about €80–€150/year, depending on insurance company
3. Earthworks
Removal of excess soil (normal soil conditions) for cellar, about €1,500
Internal development (wastewater / rainwater pipes), about €2,500 – depending on pipe route
Inspection shafts, soakaway or infiltration shaft, about €1,900–€2,200
Reserve for additional foundation costs about €8,000
4. House connection costs
Electricity/gas/water/telecom, connection to the sewer, about €8,000–€8,500 – varies by municipality
5. Fees
Acceptance of drainage pipe, about €150 – varies by municipality
Chimney sweep (inspection of the chimney / gas system – note fee applies twice), about €200 – varies by municipality
Cadastral office (transfer of data from the surveyor into the property map), about €150 – varies by municipality
Total approx.: Euro 35,000–40,000
Important: The costs for painting, floor coverings, and outdoor facilities are not included in the above list!
... if you take these costs into account – they also apply in Bavaria and can be 5 to 8% higher – and still have some leeway, it also fits with the extras
Kind regards