11ant
2019-10-13 16:05:32
- #1
I was thinking less about the consequence of in-house construction management on the site (in the mere sense of the plan-actual comparison of executed trades). Rather, about the problem that F is working slowly and shifts the other trades so much that, because M is not available until much later, M now suddenly has to come before K, which causes K and L a lot of fiddling and overhead hours. But well, that little bit of household can't be that hard, says Johanna von Koczian's husband