Exterior facilities not finished

  • Erstellt am 2016-07-08 14:58:46

ypg

2016-07-08 21:18:44
  • #1
Yes, you used the defect in the execution of the paving work to change your material on 14.06. of this year. To summarize the last posts. Edit: we are asking because you give imprecise answers.
 

wrack

2016-07-08 21:25:10
  • #2
I only changed the terrace slabs, everything else remained the same. Selected in July 2015. At that time, we did not even have an offer, not even for the previously selected terrace slabs.
 

Legurit

2016-07-08 22:29:47
  • #3
I would honestly also approach the matter a bit more calmly - garden landscaping, for example, is also heavily weather-dependent - someone can also get sick or simply a mistake can happen in the planning.
 

toxicmolotof

2016-07-08 22:47:06
  • #4
Wait a minute... you didn’t have an offer for the paving work and the terrace work on 14.6. (to clearly mention both) and then you wonder why these things are not yet finished?

And if you didn’t have an offer, is it even part of the main contract or rather a kind of special request?
 

f-pNo

2016-07-08 23:13:55
  • #5
I'll try to summarize what I've read here. Let's see if I understood it correctly:

In 2015, you discussed/agreed with the developer which paving should be done. This paving of the sidewalks and the garage driveway was only partially carried out after 15.06.2016 (at your insistence). Actually, your terrace was supposed to be built by 15.06.2016 as well. However, this did not happen – you had not even received an offer for it by 14.06.2016. You used this opportunity to change the terrace slabs again. This change is cited by your developer as the reason why he could not deliver all his services (including the paving) on time (which he had not performed until one day before the deadline).

You now want compensation for the delay in the paving. You are consciously excluding the terrace from this claim. There are no contractual compensation payments stated for the client in case of delays.

Well – I can understand the frustration. However, you might be using a sledgehammer to crack a nut here – especially since the partial paving was carried out with a (in my view) acceptable delay and the rest will probably come within a foreseeable time. In my view, you also lack the basis for a claim, as nothing was contractually agreed to regarding this.

Moreover – the weather conditions this year have already been mentioned. Even if you write that the past weeks were not so bad for you, there surely was also a time this year when the weather did not allow work. Such days are usually excluded from claims contractually.

Talk to your developer and try to agree on prompt completion. In my opinion, a "head against the wall" approach doesn’t help here, but rather mutual willingness to come together.
 

wrack

2016-07-09 09:57:35
  • #6
Correct. By 15.06, the outdoor facilities should have been completed, as stated in the contract. This has not happened. As described, it is only about the fact that it should have been finished (40 sqm of paving work).

In recent months, it has not rained as much here as, for example, in BaWü. The Brocken kept away all the showers. We have not had a drought period, but the excuse that paving could not be done here due to the weather cannot be accepted.

As already described, paving was done first at our neighbors who have not yet moved in.. This makes the "acceptable" become unacceptable.
 

Similar topics
06.02.2013Developer says: No more insulation!12
23.03.2011Developer or architect?15
26.09.2011Finding tiles from other manufacturers / sample selection for builders13
09.07.2012Developer offer for single-family house - Are the construction costs acceptable?16
16.07.2012The builder "outsources" fixed-price services to subcontractors12
03.08.2012Contract Supplement to the Construction Contract by the Developer36
30.09.2012Developer - Is withdrawal from the purchase contract possible?11
01.12.2014Real estate transfer tax / what is the tax applied to? Which developer MUST?30
18.02.2014Massive problems with the builder - is contract termination possible?33
23.06.2014Developer charges heavily for replanning - justified?12
08.10.2014How do you search for a suitable property developer?30
27.02.2015Construction project with a developer without an official building plan, is a down payment required?12
01.03.2015The developer does not build according to the plan14
15.04.2015Duplex construction: Joint or separate developer?20
13.06.2015New construction with developer / construction drawing documents23
09.09.2015Buy land separately from the developer13
15.10.2017Cost of paving work per sqm, what did you pay?34
17.03.2018Terrace slabs - Which shade: Gray, beige or sandstone13
03.08.2018Laying terrace slabs - How to proceed best - Tips?11
11.02.2021Is terrace slab thickness under 2 cm also okay?12

Oben