Drying time of the prefabricated cellar until the installation of the prefabricated house

  • Erstellt am 2024-04-22 13:22:47

DachDrueber

2024-04-22 13:22:47
  • #1
Hello everyone,
we have received very different statements on the topic of drying time for the prefabricated basement during the planning for a prefabricated house:

- Extreme 1: A prefabricated basement can be built on two days after installation. Although the concrete only reaches its nominal strength after 28 days, the significantly load-bearing parts have already dried beforehand and have their nominal strength. The residual moisture of the poured transitions can continue to dry out.
Claim: Those who want to let it dry for a long time do this only to bridge the long delivery times of the prefabricated house.

- Extreme 2: A prefabricated basement should dry out easily for 8-12 weeks to reliably achieve drying.
Claim: A shorter drying time is only intended to lure customers with short construction times.

Does anyone have an assessment regarding this?

Thanks!
 

Harakiri

2024-04-22 13:30:46
  • #2
I would quickly remove the 2-day period from my project. Even though concrete is usually sufficiently hard after 7 days (as a rule – outside temperature can have a big impact here!), and the remaining 3 weeks mainly account for the last 10%, you definitely don't want to put live loads on it after just one week.

Normally, the ceiling props for the ceiling have to stay there for the "28 days" – maybe most of them are removed after 7 days, but as mentioned, only self-weight, until it is fully cured.
 

nordanney

2024-04-22 13:38:20
  • #3
Extreme 1 is at least feasible, albeit unusual. First of all, concrete does not dry, but cures. Excess water passes through the walls of the basement – and the basement ceiling could not care less. So yes. You can continue building on the precast basement just as quickly as on a concrete ceiling or floor slab without a basement. Construction continues there almost seamlessly. Just make sure the basement is properly ventilated.
 

DachDrueber

2024-04-22 14:02:05
  • #4
Thank you all in advance for your answers! The provider of "Extrem 1" is, in our opinion, a reputable one. Hence our surprise. Addition: The basement is to be set and poured in winter. According to provider 1, this is advantageous for curing when it is cold, but there are no temperatures significantly below 0 °C. I will now assume that around 28 days of drying time are rather sensible, even for prefabricated basements.
 

hanghaus2023

2024-04-22 14:02:17
  • #5
I see it the same way as . If you are in a hurry.
 

nordanney

2024-04-22 14:05:09
  • #6
May be sensible, but it is unrealistic in practice. As with all concrete work in new construction. You don’t wait four weeks for every floor slab. It always continues a few days after concreting.
 

Similar topics
09.10.2016Roofing - Clay or Concrete?16
21.09.2023Experiences with Glatthaar Fertigkeller21
07.09.2017Floor slab: Concrete or wooden beam ceiling - Advantages and disadvantages!?20
20.02.2016Basement made of watertight concrete - switch problem12
22.12.2016Is rain harmful to concrete slabs?12
08.07.2016Concrete under downspout of roof gutters13
13.10.2016Removing tiles from concrete16
10.07.2017WU concrete + flush-mounted boxes in the residential basement - how can this be solved?35
27.08.2017Rust spots on concrete - ceiling to wall - new construction12
29.12.2020Y-Tong vs Concrete without extra insulation in practice (heating costs)38
14.12.2019Connecting Concrete Flush Boxes | DALI Circuit10
30.06.2020Base plate, too little cement in the concrete19
08.07.2020Concrete fence posts widen18
24.03.2021Cracks detected in basement concrete exterior wall, how to proceed?33
06.05.2021New building with basement | WU concrete plus ring drainage21
17.09.2021Casting concrete paving stones yourself12
05.04.2022Attic roof - wood or concrete cheaper?10
14.04.2022Are there polygonal concrete slabs on the market?13
12.01.2023Prefabricated garages concrete and steel, current prices?21

Oben