Drying time of the prefabricated cellar until the installation of the prefabricated house

  • Erstellt am 2024-04-22 13:22:47

DachDrueber

2024-04-22 13:22:47
  • #1
Hello everyone,
we have received very different statements on the topic of drying time for the prefabricated basement during the planning for a prefabricated house:

- Extreme 1: A prefabricated basement can be built on two days after installation. Although the concrete only reaches its nominal strength after 28 days, the significantly load-bearing parts have already dried beforehand and have their nominal strength. The residual moisture of the poured transitions can continue to dry out.
Claim: Those who want to let it dry for a long time do this only to bridge the long delivery times of the prefabricated house.

- Extreme 2: A prefabricated basement should dry out easily for 8-12 weeks to reliably achieve drying.
Claim: A shorter drying time is only intended to lure customers with short construction times.

Does anyone have an assessment regarding this?

Thanks!
 

Harakiri

2024-04-22 13:30:46
  • #2
I would quickly remove the 2-day period from my project. Even though concrete is usually sufficiently hard after 7 days (as a rule – outside temperature can have a big impact here!), and the remaining 3 weeks mainly account for the last 10%, you definitely don't want to put live loads on it after just one week.

Normally, the ceiling props for the ceiling have to stay there for the "28 days" – maybe most of them are removed after 7 days, but as mentioned, only self-weight, until it is fully cured.
 

nordanney

2024-04-22 13:38:20
  • #3
Extreme 1 is at least feasible, albeit unusual. First of all, concrete does not dry, but cures. Excess water passes through the walls of the basement – and the basement ceiling could not care less. So yes. You can continue building on the precast basement just as quickly as on a concrete ceiling or floor slab without a basement. Construction continues there almost seamlessly. Just make sure the basement is properly ventilated.
 

DachDrueber

2024-04-22 14:02:05
  • #4
Thank you all in advance for your answers! The provider of "Extrem 1" is, in our opinion, a reputable one. Hence our surprise. Addition: The basement is to be set and poured in winter. According to provider 1, this is advantageous for curing when it is cold, but there are no temperatures significantly below 0 °C. I will now assume that around 28 days of drying time are rather sensible, even for prefabricated basements.
 

hanghaus2023

2024-04-22 14:02:17
  • #5
I see it the same way as . If you are in a hurry.
 

nordanney

2024-04-22 14:05:09
  • #6
May be sensible, but it is unrealistic in practice. As with all concrete work in new construction. You don’t wait four weeks for every floor slab. It always continues a few days after concreting.
 

Similar topics
09.10.2016Roofing - Clay or Concrete?16
21.09.2023Experiences with Glatthaar Fertigkeller21
07.09.2017Floor slab: Concrete or wooden beam ceiling - Advantages and disadvantages!?20
19.10.2015Concrete platform stairs?14
20.02.2016Basement made of watertight concrete - switch problem12
22.12.2016Is rain harmful to concrete slabs?12
28.11.2019Concrete vs. Clay Roof Tiles26
08.07.2016Concrete under downspout of roof gutters13
26.04.2021House made of concrete without additional insulation - monolithic12
01.02.2017Basement originally partially concrete, now possibly completely brick-built28
27.08.2017Rust spots on concrete - ceiling to wall - new construction12
29.12.2020Y-Tong vs Concrete without extra insulation in practice (heating costs)38
14.12.2019Connecting Concrete Flush Boxes | DALI Circuit10
27.04.2020Entrance platform front door concrete17
23.04.2020Are additives avoidable in concrete?20
12.11.2020Create sidewalk and parking lot from concrete26
30.06.2020Base plate, too little cement in the concrete19
08.07.2020Concrete fence posts widen18
17.09.2021Casting concrete paving stones yourself12
14.04.2022Are there polygonal concrete slabs on the market?13

Oben