Drying time of the prefabricated cellar until the installation of the prefabricated house

  • Erstellt am 2024-04-22 13:22:47

ypg

2024-04-22 20:28:46
  • #1
In principle, it doesn't matter when it comes to the positioning of the house. The manufacturing of the house takes its time, and logistics usually involve more than just the net production time. However, contractors can often estimate whether the house can be delivered in 15 or 18 minutes. If you want to build with a basement, it will be constructed beforehand at some point. Whether a basement cures for 72 hours or 31 days will not significantly affect the positioning of the house. One client may think this way on one hand, while on the other, there is a company that wants to make many clients happy. This is only possible with good planning.
 

filosof

2024-04-24 07:49:57
  • #2
Setting up the house two days after the basement concreting may be technically possible. In reality, however, hardly feasible. After concreting, the sealing still needs to be done, the [Ringerder] installed, the working space backfilled, and the scaffolding erected. All this within 48 hours and then the trucks and the crane are already ready – I don't believe that...
 

filosof

2024-04-24 07:59:27
  • #3


P.S.: By the way, from my own experience, I advise against such a tight schedule. If anything goes wrong during basement construction that delays the process by a few days, the date for setting the house will be missed and will likely be postponed by a few weeks or even months until it can be rescheduled. For us, it rained when the sealing was supposed to be applied – not possible. The crew then had to move to another construction site, and I really had to escalate the matter so that another crew came and finished it one week before the setting date – then the other work (see above) was carried out and just barely finished before the crane arrived...

The original plan was three weeks between basement and house. Today, for purely organizational reasons, I would insist on at least 6 weeks. Technically, I would trust the competence of the general contractor/basement builder. If that were not given, I would look for another one from the start...
 

DachDrueber

2025-01-06 11:36:00
  • #4
Current status of our basement-house schedule: (Completed) Basement construction week 3 (+ beginning week 4) House construction: week 7 According to the basement company Glatthaar, this schedule is suitable
 

Similar topics
28.01.2010House with or without a basement? - Experiences20
18.08.2013Massive house with basement. Is our budget enough?11
03.03.2012Position controlled residential ventilation in the underground basement?16
09.06.2013Costs of earthworks without basement15
19.04.2013Budget for the construction of a single-family house with a WU concrete basement27
29.01.2014Cost saving/basement/affordable tiles/sealed screed?13
05.07.2014Sleeping in the basement okay?14
06.11.2014Houses without basements: Storage space, hobby basement?49
20.08.2016Move the office to the basement?20
09.04.2015Sacrifice the basement for 20m² more living space?15
14.04.2015Questions about planning a single-family house in Hamburg - Additional costs due to the basement11
27.05.2015Does an external chimney have to go down to the basement?12
27.08.2015House with or without a basement35
24.10.2015Built without a basement & regretted?77
21.02.2016Is wastewater drainage possible in the basement?18
27.01.2016Without a basement - where to put the workshop/hobby room (pictures?)11
26.12.2018Omit basement windows in ventilated basements?20
20.02.2016Basement made of watertight concrete - switch problem12
23.03.2016Crane positioning: street/neighbour/railway mast29
08.03.2016Which basement have you decided on?13

Oben