Drying time of the prefabricated cellar until the installation of the prefabricated house

  • Erstellt am 2024-04-22 13:22:47

ypg

2024-04-22 20:28:46
  • #1
In principle, it doesn't matter when it comes to the positioning of the house. The manufacturing of the house takes its time, and logistics usually involve more than just the net production time. However, contractors can often estimate whether the house can be delivered in 15 or 18 minutes. If you want to build with a basement, it will be constructed beforehand at some point. Whether a basement cures for 72 hours or 31 days will not significantly affect the positioning of the house. One client may think this way on one hand, while on the other, there is a company that wants to make many clients happy. This is only possible with good planning.
 

filosof

2024-04-24 07:49:57
  • #2
Setting up the house two days after the basement concreting may be technically possible. In reality, however, hardly feasible. After concreting, the sealing still needs to be done, the [Ringerder] installed, the working space backfilled, and the scaffolding erected. All this within 48 hours and then the trucks and the crane are already ready – I don't believe that...
 

filosof

2024-04-24 07:59:27
  • #3


P.S.: By the way, from my own experience, I advise against such a tight schedule. If anything goes wrong during basement construction that delays the process by a few days, the date for setting the house will be missed and will likely be postponed by a few weeks or even months until it can be rescheduled. For us, it rained when the sealing was supposed to be applied – not possible. The crew then had to move to another construction site, and I really had to escalate the matter so that another crew came and finished it one week before the setting date – then the other work (see above) was carried out and just barely finished before the crane arrived...

The original plan was three weeks between basement and house. Today, for purely organizational reasons, I would insist on at least 6 weeks. Technically, I would trust the competence of the general contractor/basement builder. If that were not given, I would look for another one from the start...
 

DachDrueber

2025-01-06 11:36:00
  • #4
Current status of our basement-house schedule: (Completed) Basement construction week 3 (+ beginning week 4) House construction: week 7 According to the basement company Glatthaar, this schedule is suitable
 

Similar topics
28.01.2010House with or without a basement? - Experiences20
05.06.2010Basement made of high perforated bricks or concrete?11
18.08.2013Massive house with basement. Is our budget enough?11
08.12.2015Construction costs for KFW70 house with basement turnkey15
03.03.2012Position controlled residential ventilation in the underground basement?16
26.10.2012External perimeter insulation floor slab, basement mold risk11
09.06.2013Costs of earthworks without basement15
19.04.2013Budget for the construction of a single-family house with a WU concrete basement27
27.05.2013Cost estimation: prefabricated house, basement, carport, single garage10
01.07.2013Additional insulation in the Ytong basement (36 cm)14
27.07.2013Average construction time for a semi-detached house with a basement11
16.02.2014Floor plan of a single-family house with basement - Your opinions, please16
29.01.2014Cost saving/basement/affordable tiles/sealed screed?13
19.03.2014Cost for a new single-family house, 2 full floors, without basement18
05.07.2014Sleeping in the basement okay?14
13.08.2014Water intrusion in basement due to storm - insurance?17
03.02.2017Single-family house 2 floors without basement - floor plan - costs - feasibility?24
31.12.2014Get training equipment in the basement (new building)?14
23.03.2016Crane positioning: street/neighbour/railway mast29
22.12.2019Crane from the neighbor on my property67

Oben