jens_weller
2011-10-19 12:25:37
- #1
Hello everyone.
I have a question regarding a construction cost overrun related to self-performed work. We built at a fixed price. However, some things were done as self-performed work. For these, the costs for the materials were estimated by the architect so that we would not exceed our financial framework. However, the costs for the self-performed work were now much higher. For example, we planned the garage completely as self-performed work. The architect estimated about €10,000 here. However, the garage now costs over €20,000. This calculation only includes material costs. Any labor costs (e.g., gate installation) or additional costs due to special requests (electric drive) that have arisen were not included.
An overrun of 100%, and this only for the garage. What is the legal situation here regarding construction cost overruns? I hope you can help me. Many thanks in advance.
I have a question regarding a construction cost overrun related to self-performed work. We built at a fixed price. However, some things were done as self-performed work. For these, the costs for the materials were estimated by the architect so that we would not exceed our financial framework. However, the costs for the self-performed work were now much higher. For example, we planned the garage completely as self-performed work. The architect estimated about €10,000 here. However, the garage now costs over €20,000. This calculation only includes material costs. Any labor costs (e.g., gate installation) or additional costs due to special requests (electric drive) that have arisen were not included.
An overrun of 100%, and this only for the garage. What is the legal situation here regarding construction cost overruns? I hope you can help me. Many thanks in advance.