I can gladly do that. Here is a list with the approximate values. However, I have to say that my dad runs a small building materials business for ecological building materials and therefore some materials were sourced through equity.
Heating / Water / Sewage (Total costs: 29,500 Euro):
Own work (Material: 1,000 Euro):
- Removing old radiators and pipes / conduits and making grooves and shafts for new pipes / conduits
- Masoning heating niches
External work (28,500 Euro):
- Tank disposal
- Gas connection
- New heating (gas) / radiators / pipes / conduits
Electrical (Total costs: 6,000 Euro):
Own work (Material: 3,000 Euro):
- Grooving (opening and closing)
- Installing main distributor and two sub-distributors
- Pulling cables
- Purchasing and wiring sockets and switches
External work (3,000 Euro):
- Wiring of main and distributor boxes + inspection
14 windows / 1 door (Total costs: 5,000 Euro):
Own work (Material: 3,300 Euro):
- Removing and disposing old windows
- Ordering new windows via the Internet
External work (1,700 Euro):
- Installation by local carpenter
Roof insulation ([U]Total costs: 4,000 Euro)[/U]
Own work (3,500 Euro):
- Covering area, vapor barrier, insulating, underlay, new battens, roofing
- Substructure, 20 cm cellulose fill
- New attic stairs
External work (500 Euro):
- Scaffolding
Bathroom 6 m² and WC 3 m² ([U]Total costs: 10,000 Euro):[/U]
Own work (Material: 5,000 Euro)
- Gutting
- Bathroom equipment ordered via Internet
- Tiles from Bauhaus
- Installation sanitary
External work (5,000 Euro):
- Tiling
- Shower enclosure with installation
Floor ([U]Total costs: 8,000 Euro)[/U]
Own work (Material: 8,000 Euro):
- Removing old floors (carpet)
- Laying new floor
Walls ([U]Total costs: 10,000 Euro):[/U]
Own work (Material: 2,500 Euro):
- Removing old wallpaper
- Material procurement
- Primed
- Helped a bit
External work (7,500 Euro):
- Fine lime plaster downstairs
- Painter’s fleece + textured paint upstairs
Interior doors ([U]Total costs: 5,000 Euro):[/U]
External work:
- Completely new (9 pcs. completely by local carpenter including installation)
The remaining approx. 10,000 Euro went for waste and construction debris disposal as well as for small items (a bit of masonry, paint, etc.)