Building in existing structures - Subsequent additional costs despite a fixed price

  • Erstellt am 2023-02-26 20:56:22

SoL

2023-02-27 15:38:18
  • #1

Great, it's nicely sloppy.
He can give you the cheapest of the cheap or process his leftover stock.
It should say "16cm mineral wool WLG0xx manufacturer product."

Regarding the wording: Most inaccuracies are at the customer's expense because you have concluded a contract for work. The contract describes the work to be performed in return for payment.
And if you do not describe the work in certain specifics or do so insufficiently (see mineral wool), the contractor has freedom of choice because no binding contractual requirements exist.
 

Berlinho2

2023-02-27 15:48:53
  • #2
I completely agree with you that many things are way too unspecific and that I was simply naive about it. I have come to terms with that mentally as well. However, the relevant part and what this was primarily about was specified as "extension to the existing basement" including reference to the historical execution documents, to which at least the basement floor plan in the contract plan refers. Thus, he has indeed committed to deliver this work. How do you specifically assess this point? What do you see as a fair solution here?
 

SoL

2023-02-27 16:46:51
  • #3
Doesn't matter what I consider fair. Have a specialist lawyer take a look or think of something. With 50/50, you often get close to acceptance between two parties ;)
 

hanghaus2023

2023-02-27 17:54:00
  • #4
In my opinion, the insufficient description of the contract is at the expense of the contractor. As a specialist, he should have either checked the static calculations before signing the contract or fixed a corresponding reservation in the contract. Since he probably would have jeopardized your signature by declaring the reservation, he took the risk of signing the contract without checking the static calculations. If there was previously a prefabricated house on it, he should actually have assumed that the basement would not support the solid house.

I am not a lawyer. Therefore, you should definitely seek legal advice.

Giving in already does not protect you from further additional charges. Rather, the contractor sees that he can get away with it with you.

Show me the additional charge that is supposed to cost 20k. The justification for the extra costs can also be quite interesting.
 

SoL

2023-02-27 18:22:47
  • #5

Getting the right vs. getting the house.
You have to know.
 

K a t j a

2023-02-27 18:38:03
  • #6
How much work has been done so far? Has anything happened at all, or would each party be in the same position as before the contract was concluded if the contract were terminated?
 

Similar topics
16.06.2011Conclude a construction contract under reservation?10
13.09.2012Feeling pressured into a contract, is that normal?17
29.09.2011Is construction pre-planning without signature / contract legally valid?12
16.05.2015Contract unclear: humus earth collectors10
23.08.2015Construction financing with a fixed-term contract13
04.07.2016Building without a contract - Concerns?39
10.09.2016Construction financing and contract with the developer24
28.09.2016Question about early repayment and clause in the contract41
28.05.2017Plundering the Riester contract - for less need for credit?16
16.08.2018Civil engineering works without a contract - normal, experiences?10
04.01.2022Architect, contract according to HOAI 2013 - refuses to provide service36
06.06.2019Completion date in General Contractor Agreement - Wording assistance62
28.10.2019Received an offer for my shell construction18
05.08.2020Contract for land purchase - obligation to build within 2.5 years18
11.11.2020Cancellation of a contract with a plumbing company24
09.05.2021Price adjustment clause in the contract with the general contractor18
30.03.2022Terminate the contract with the general contractor "early"22
27.01.2024House purchase through agent, now contract terminated18

Oben