Price adjustment clause in the contract with the general contractor

  • Erstellt am 2021-05-06 20:31:47

hanghaus2000

2021-05-07 10:42:03
  • #1
The forum can hold whatever opinion it wants. It is totally off-topic anyway.
 

Acof1978

2021-05-07 10:51:13
  • #2
In my case, I agreed to an offer from the construction company. Afterwards, a planning contract was drawn up, where initially only up to the building permit is paid. It was about 14,000 €. If the building permit fails or the financing does not work out, it remains at 14,000 € and we part ways. If it continues, the 14,000 € will be deducted from the offer value. He has also already reported the construction site to his suppliers and secured the prices. Just yesterday I inquired whether the offer prices remain. He said the increase only applies to new contracts.
 

Jann St

2021-05-07 13:06:46
  • #3
Hi,

I think price adjustment clauses should not be agreed upon (if you are the client). For steel, for example, it is customary – there is a price commitment for the expected necessary period, and if the construction time exceeds that period, the price should be renegotiated. Either the contractor trusts themselves to do it or not. That is their entrepreneurial risk (at least that’s how I see it). A price adjustment clause takes away all their risk, which is unfair. The calculation includes AGK+BGK+WuG (i.e. general business costs, site overheads, risk and profit) – with such a clause, they pass their risk on in the supplier prices. If at all, as already described, it can be stated that prices are to be renegotiated if there is an increase of +50% – but that is not very nice for the client.

Regarding the question of whether price increases should generally be passed on to the client, it is a very difficult question. I would answer “no.” The exception would be a construction period delay for which the client is responsible, from which rising prices result. These rising prices cannot be demonstrated through supplier contracts (which are easily manipulated) but through price indices that exist for common building materials. But here too, the contractor has to factor in normal fluctuations. What about Corona and the resulting consequences? In my opinion (and I am not a lawyer), the contractor must include strong price fluctuations and supply bottlenecks in their calculation if the offer was submitted after April 2020, because they had to be expected.

Of course, the question remains: If you don’t sign the contract, will you find someone who will do it cheaper? If there was already a contract (and that’s how I understand it), a price adjustment clause cannot be added retrospectively. Also, the client refusing is not a reason for termination by the contractor.

These are, of course, all my personal impressions, as someone who is professionally both contractor and client (site manager at a general contractor).

Best regards, Jann
 

Julia321

2021-05-07 14:48:16
  • #4
Hello everyone,

thank you in advance for the answers!

So far, we have not signed a contract with a final amount. We had one given to us in advance to see what is stated there with the clause.

So far, we have only signed the planning contract and paid the architect.
 

11ant

2021-05-07 22:30:27
  • #5
The margins of the general contractor (GU) in single-family house projects are of such magnitude that price increases can easily consume the entire profit – including the necessary operating profit. It is reasonable, and thus in the interest of all parties involved, that a GU devises risk mitigation measures, as the alternative would be to file for insolvency proceedings proactively upon accepting the contract. I am only opposed to the approach that the GU, in his "distress" (not seeking advice on how to handle this legally properly – although the quality of advice contained in his IHK contribution might already be sufficient), resorts to an unsuitable formulation. Even without accusing him of bad faith, the formulation under discussion here is a black box with explosive potential for the builder.
 

Joedreck

2021-05-08 07:43:18
  • #6
Then the contractor just has to set the fixed price correspondingly high. As is customary. Fixed prices always include a risk premium to cover eventualities. But the way it is formulated... Huii
 

Similar topics
16.06.2011Conclude a construction contract under reservation?10
13.09.2012Feeling pressured into a contract, is that normal?17
29.09.2011Is construction pre-planning without signature / contract legally valid?12
22.09.2012Who else fell for a contract with a reservation clause? - Search13
16.05.2015Contract unclear: humus earth collectors10
23.08.2015Construction financing with a fixed-term contract13
04.07.2016Building without a contract - Concerns?39
10.09.2016Construction financing and contract with the developer24
28.09.2016Question about early repayment and clause in the contract41
28.05.2017Plundering the Riester contract - for less need for credit?16
16.08.2018Civil engineering works without a contract - normal, experiences?10
02.11.2018Is the bad weather clause applicable as an excuse for the general contractor?10
04.01.2022Architect, contract according to HOAI 2013 - refuses to provide service36
06.06.2019Completion date in General Contractor Agreement - Wording assistance62
05.08.2020Contract for land purchase - obligation to build within 2.5 years18
11.11.2020Cancellation of a contract with a plumbing company24
02.04.2021Change of optics to avoid defects10
02.06.2021Contract work price increases rights10

Oben