Thomas911
2021-07-25 11:53:14
- #1
What communication has taken place so far? Is there still room for a solution?
As a construction contractor, I probably wouldn’t be happy either if my client does not make the agreed payment at the first go, or only pays late. Was this agreed like that between you and the company, so that there was consensus on the procedure?
Otherwise, I can understand that one wants to protect oneself from not being paid for the service provided.
You write about friction, but I would still be missing further context..
I will now try to answer the questions one by one.
1) Regarding this, we have not had much discussion yet. The managing director mentioned by phone that he would like to have the following document. We will talk about it in detail during the execution planning in a personal meeting.
2) The payment delay occurred because the bank refused to transfer the first installment to the construction company without being registered in the land register. The registration took a bit longer, which caused a payment delay of 5 days. The construction company was immediately informed after the related conversation and verbally it was "no problem." There was no written extension of the payment deadline – which was our oversight.
3) The friction so far concerned the architectural management, the soil survey, and the earthworks. I recently opened two threads about this. In the first case, the architect gave us terrible advice and made many mistakes in the planning. Even after several rounds of corrections, various mistakes occurred, so that we have been unable to obtain a building permit for 3 months and have been excluded from the simplified procedure. The second point involved the construction company commissioning a soil survey and then suddenly refusing to provide it to us, although the opposite had been agreed beforehand. The justification: they had commissioned the soil survey for themselves and are not obliged to share it with us. To what extent the earthworks are to be carried out, we have not been allowed to find out before the execution planning appointment. To us, this appears non-transparent. Furthermore, we were told that the construction company does not allow a third party to carry out the earthworks under the house. Contractually, it is not stipulated that the earthworks must be carried out only by them. The justification is partly understandable: they will build the house on it and cannot be liable for third-party work.
All in all, many discrepancies are arising even before construction begins, which cause us distrust.