BÜ wants a declaration of assignment. How to avoid it?

  • Erstellt am 2021-07-25 10:02:16

Thomas911

2021-07-25 11:53:14
  • #1


I will now try to answer the questions one by one.

1) Regarding this, we have not had much discussion yet. The managing director mentioned by phone that he would like to have the following document. We will talk about it in detail during the execution planning in a personal meeting.

2) The payment delay occurred because the bank refused to transfer the first installment to the construction company without being registered in the land register. The registration took a bit longer, which caused a payment delay of 5 days. The construction company was immediately informed after the related conversation and verbally it was "no problem." There was no written extension of the payment deadline – which was our oversight.

3) The friction so far concerned the architectural management, the soil survey, and the earthworks. I recently opened two threads about this. In the first case, the architect gave us terrible advice and made many mistakes in the planning. Even after several rounds of corrections, various mistakes occurred, so that we have been unable to obtain a building permit for 3 months and have been excluded from the simplified procedure. The second point involved the construction company commissioning a soil survey and then suddenly refusing to provide it to us, although the opposite had been agreed beforehand. The justification: they had commissioned the soil survey for themselves and are not obliged to share it with us. To what extent the earthworks are to be carried out, we have not been allowed to find out before the execution planning appointment. To us, this appears non-transparent. Furthermore, we were told that the construction company does not allow a third party to carry out the earthworks under the house. Contractually, it is not stipulated that the earthworks must be carried out only by them. The justification is partly understandable: they will build the house on it and cannot be liable for third-party work.

All in all, many discrepancies are arising even before construction begins, which cause us distrust.
 

Thomas911

2021-07-25 11:56:07
  • #2
I have summarized our previous points of contention that have weakened our trust in the reply to .
 

Myrna_Loy

2021-07-25 11:58:09
  • #3
If everyone else apparently makes malicious and careless mistakes, then maybe one should ask whether one is adopting a perspective that does not fit the situation? Hanlon's Razor?
 

ypg

2021-07-25 12:01:02
  • #4
We have also worked out halfway through point 3 here that everything is correct as it is. You should then remove this from your list of distrust. It may be the same with other points. For architectural services, there are often only "limited services" for BUs, as the diligent reader here knows.
 

Thomas911

2021-07-25 12:02:52
  • #5
Emmm, I have written multiple times that the mistake lies with us. My question was not about who is right or wrong, but whether there are ways to save the situation and spare us the assignment declaration / guarantee.
 

hanghaus2000

2021-07-25 12:04:20
  • #6


If you don’t want to continue building with the contractor, then termination is the only option. Whether you terminate or provoke termination by not paying or not providing the bank guarantee does not, in my opinion, make a financial difference.

Maybe the termination clause would help us further to assess this.
 

Similar topics
09.06.2013Costs of earthworks without basement15
15.01.2013Soil survey report for house construction10
22.08.2013Are the estimated costs of the general contractor for earthworks reasonable?12
07.03.2014Earthworks are starting, but I need a tip.12
26.04.2016Sand, gravel, and other earthworks32
28.09.2016Evaluation of earthworks offer14
28.08.2017Earthworks: Making the right choice of provider14
29.12.2017Is it possible to found a single-family house without concrete and earthworks?21
25.01.2018Earthworks and shell construction, who bears the warranties?10
29.10.2018Earthworks in the construction performance description17
08.04.2019Earthworks costs in Bavaria15
14.06.2019Costs for earthworks18
08.09.2020Earthworks costs, hillside house14
23.07.2021Earthworks... Dispute with the occupational disability insurance20
27.11.2021Ancillary construction costs for earthworks according to soil report16
15.03.2022Cost planning for earthworks33
29.04.2022Designing hillside property - Earthworks / Retaining wall cost options26
10.05.2022Carry out earthworks with equity capital?10
07.02.2025Cost issue for earthworks on a slope22

Oben