Was there a soil survey before? Did the GC require one before demolition?
I don’t think this was done. I asked the architect and GC once at the beginning, but the architect said it was not necessary at that time, and I failed to check again :(.
Did the basement have to be removed? Couldn’t it have been kept?
Yes, it is at a different location and has a different size.
You are the builders, right?
Yes
The 8 months will be very tight. Do yourself a favor and don’t make the mistake of putting pressure on – don’t terminate the apartment yet.
From other threads I understood that 8 months are normal if the work starts under good weather conditions. I was mainly worried that it might be too late to start the work because winter is coming. I am not sure when I should start counting the 8 months.
I only see information from the soil report here. No planned excavation pit. Also no retaining structure (sheet piling) planned.
Yes, unfortunately I don’t have a plan for the excavation pit. The retaining structure is also not planned yet. I am still waiting for that to be done.
Why? It should be clear to everyone that one guarantee does not solve the problem. Your site manager and you should by now also be aware that an unsupported excavation pit can affect the street. The costs of repair are borne by whoever causes the damage.
Sorry, that’s my mistake. I didn’t understand why “guarantee” was mentioned here, then I realized that I mistakenly used it in my first post while I meant “retaining structure” – that is the Berlin sheet piling :rolleyes:
This is a two-story house on a ground slab, the slab is already suspended in the area of the foil underneath. The outer walls stand on it and load the slab in bending.
I am not sure how high the load is here since it is a very old prefab house, but it definitely seems dangerous. I also reported this problem to the GC, but it’s strange that this neighbor has not complained yet!
My summary of what I understood is five letters short: “nothing” (and even there I am not quite sure). The OP and his co-builder obtained a building permit here, which I already do not understand: the land registry excerpt shows the neighboring house No. 18 on 367/21 and the predecessor building on the OP’s property in a position that would allow assuming a setback waiver by the previous owner. So I don’t even follow the simple boundary distance to the neighbor here. Then I read here about a basement of the existing building, which I don’t recall being mentioned in the OP’s previous thread – so it’s unexpected to me to have a deep demolition. Then I see here an “excavation pit” as for a basement of the duplex: the slope seems to contain a working space that seems overly generous to me just for a deep demolition. Not that I had assumed the predecessor building to be basement-less – but I had for the new building. So I had indeed expected a deep demolition rather than just backfilling the existing basement, but of course then secured with sheet piling or similar to prevent unwanted formation of a working space between the deep demolition and the neighboring boundary. I find it strange that I as a construction consultant (by profession but theoretically seen) think further here than a construction contractor (for whom this should be everyday practice). Furthermore, I am then surprised that this “excavation pit” might actually be a construction pit (for the new basement), because otherwise it would have had to be immediately / almost simultaneously backfilled and compacted. So I assume a regrettably architect-less planning here: that is, a general contractor was apparently engaged who virtually overplanned the still-built property unrealistically like a planum. If I sat at the building authority, I would have at least conditioned the building permit on submission of a demolition schedule. This looks to me like such a textbook foolishness that I suspect the mayor of @goalkeeper might have found a new field of activity here. Ceterum censeo, the tax rate on thoughtlessness must urgently be increased.
The plan was to complete the excavation pit together with the demolition of the old house with basement without waiting time. Due to poor planning (or completely missing planning), it became apparent during execution that some additional measures had to be taken that were not planned, so the excavation was stopped in the middle of the work.