Behavior in case of imminent delay by the property developer

  • Erstellt am 2023-07-29 15:10:38

rasudiger

2023-07-30 09:48:42
  • #1

Yes, July this year. We financed in July 2022. Of course, a disbursement of the loan is not possible without construction progress.

Thanks to - that’s how we see the situation so far as well.


You seem to know the market very well. That the developer is known to be reliable pleases me of course - I hope that this will be confirmed.
 

Sunshine387

2023-07-30 11:20:17
  • #2
I know some projects of Norddeutsche Wohnbau personally and they were all completed on time. I suspect, however, that it is also common for them to start building only after at least 50% of the units are sold, and that you were simply too hasty because you still expected a strong market. But with Volksbank backing you now, I wouldn't worry too much. They will surely find a solution for you.
 

rasudiger

2023-07-31 09:43:33
  • #3
Thank you for your insight and nice to hear that you have had good experiences. The assumption that a certain share must be sold was expressed unanimously. I am curious to see what solution the developer will propose - at the current price it is apparently difficult to sell the houses and apartments.
 

xMisterDx

2023-07-31 14:22:31
  • #4
Well, what is he supposed to suggest? He has you hooked, the contract does not provide for specific compensation, and you do not even know legally whether the building permit is really final, so he could start if he wanted to.
 

rasudiger

2023-07-31 16:05:10
  • #5
According to the information from the thread, we are making an effort to obtain the BT's view on the deadlines. Then we will see further.
 

xMisterDx

2023-07-31 16:50:28
  • #6
Viebrockhaus has been advertising a construction time of 3 months for ages, which is usually adhered to. Therefore, I am surprised that you want to sound the alarm already when, according to the general contractor, it is supposed to start in November? Even if it turns out to be July or August next year. Compensation would only be owed to you if moving in is not possible in May and the general contractor has done everything to meet this date. Everything that accrues until then, such as standby interest, double burden, etc., is your problem anyway. If you don’t believe that the general contractor will start the project promptly or finish on time, although I wouldn’t make a fuss over 2 or 3 months here, then you have to get out of the contract. Everything else is endless anxiety.
 

Similar topics
06.02.2013Developer says: No more insulation!12
23.03.2011Developer or architect?15
16.06.2011Conclude a construction contract under reservation?10
13.09.2012Feeling pressured into a contract, is that normal?17
09.07.2012Developer offer for single-family house - Are the construction costs acceptable?16
16.07.2012The builder "outsources" fixed-price services to subcontractors12
30.09.2012Developer - Is withdrawal from the purchase contract possible?11
01.12.2014Real estate transfer tax / what is the tax applied to? Which developer MUST?30
13.06.2015New construction with developer / construction drawing documents23
15.03.2016Developer changes plot size25
10.09.2016Construction financing and contract with the developer24
21.07.2017Buying a terraced house from a developer - contract content?71
30.12.2017Take over the insurance from the developer after handover of keys?15
29.05.2018Buying a house from a developer - required documents33
30.08.2019Must developers indicate immense embankment height/costs?12
04.03.2019Client-side while building with a property developer16
06.01.2020House purchase, prefabricated house from the developer with land10
13.07.2020Developer does not want to offset lump-sum damages with installments19
19.03.2023Consumer construction contract, construction contract not executed - compensation for damages?44
03.10.2025Floor plan changes for end-terrace house from the developer134

Oben