Are the costs justified?

  • Erstellt am 2016-06-08 21:40:36

Peanuts74

2016-06-10 10:47:50
  • #1
Exactly, that's exactly what I mean, that you can't just generally say "Take the excavated material for backfilling!" Especially in NRW, there are virtually all kinds of soils, from stone to clayey to sandy... I just wanted to point that out before the OP thinks about saving money and fills the construction pit full of clay. Depending on the soil, it's better to take it to the landfill and get cheap sand or gravel the deeper excavation under the house. I just don't understand how the mentioned 28,000 € adds up here, does the construction company fill everything with concrete and pour a 100cm thick slab?
 

DG

2016-06-10 11:11:25
  • #2




Hello , ,

de facto, some things have to be clarified/distinguished here before anyone gets blamed:

    [*]Who recorded the heights before the building application, or from what source do the heights originate?
    [*]Who created the site plan for the building application – architect or surveyor?
    [*]Who carried out the staking out? (does not necessarily have to be done by the surveyor!)
    [*]Is there a staking out sketch?
    [*]If not – why not? Was one requested (afterwards) by the architect/builder?
    [*]If yes – are height indications from the batter board and/or manhole covers or other connection points noted there?
    [*]If yes – do these height indications differ from the preliminary/data in the building application?

Furthermore: with the massive difference of 37 cm, this should have been roughly checked/could have been noticed by the other participants in the construction. This is actually such a large deviation that in the event of a regulated damage it would likely be divided among three or four parties, namely possibly:

Surveyor, architect, civil engineer/construction contractor, and builder, whereby I strongly suspect here that the heights did not come from the surveyor – he would have had to have been in a deep sleep. Not impossible, but rather unlikely.

Best regards
Dirk Grafe
 

T21150

2016-06-10 11:25:54
  • #3


I fear something like this in this case as well. Until that is clarified – presumably a lot of time will pass. Because all parties involved will surely cheerfully toss the "It’s not my fault" balls back and forth. Time is money......(+ nerves).

Probably cheaper is: filling up....(with *suitable* material). Or just building a nice little stair or ramp to the terrace.

Of course, one can try in parallel to have one of the presumed parties responsible for the disaster bear (part of) the costs. Principle hope.

Yes – 37 cm, that is quite a mouthful, but if we look at it from a bit of a distance: definitely a solvable problem and not a complete catastrophe.

Best regards
Thorsten
 

DG

2016-06-10 11:36:56
  • #4


This is completely harmless in this case, because construction can continue. Theoretically, it is also conceivable that a mistake happens and you initially have a construction stop – here, a mistake has probably happened, but it does not delay the construction, it only causes additional costs.

The question whether the possible culprit pays for the material or the ramp is ultimately irrelevant.

Best regards Dirk Grafe
 

Peanuts74

2016-06-10 11:47:49
  • #5
I am just wondering how big the plot is or if I understood it correctly. (Assumed) 200 - 400 m² need to be raised by 37cm? With cheap backfill sand, you are looking at a very low four-digit amount... The whole hassle hardly seems worth it, and you still have the advantage of sitting a bit higher...
 

MarcWen

2016-06-10 12:55:30
  • #6


28T is completely civil engineering. So there’s a bit of small stuff included. Basement makes no difference for us, as we build on the ground.

As I said, clay is good for nothing, you can’t use it for backfilling either. When it gets wet, it’s like jelly. Didn’t want to believe it either, but I trust the experts on that.
 

Similar topics
02.01.2012Semi-detached house - who submits the building application first, wins?29
02.12.2013Are surveying costs negotiable with the surveyor?10
10.12.2012Terrain elevations in the development plan are incorrect.12
29.10.2013Property reserved, construction financing plan, architect/building permit application21
17.12.2014Building application "deferred". What does that mean?19
28.02.2015Building application submitted/open detailed questions/looking forward to suggestions39
15.06.2015Garage - Building Application - Confusion36
27.12.2015Who has built with an architect? Experiences??85
30.10.2015Can the building application be submitted this year?14
23.09.2016Architect and budget limit... insurance? possibilities25
01.02.2017Building application is becoming increasingly complicated!20
27.04.2017Carport deviation from the building application21
07.06.2017Permeable traffic areas in the building application17
04.08.2017Building application or building notification15
06.12.2017Constantly making the same mistakes in the building application - stupidity or intent?43
20.11.2020Wait with the building application because of the child construction allowance1354
05.08.2020Building a garden shed... Is a building permit necessary? Detours?17
18.02.2022Floor plan offer from the architect - your opinion11
22.11.2022Rough staking changed, excavation incorrect11
28.09.2024Architect commissions surveyor without the homeowner's consent.45

Oben