Pyrate
2018-10-16 18:39:03
- #1
Our architect has presented us with the architect contract according to HOAI. He assigns our single-family house construction project to fee zone 4 with the minimum rate (fee rate).
In addition, he estimates a flat rate for incidental costs of 8%.
Our building plot is a hillside plot (south slope). The slope runs diagonally within the building envelope with a height difference of just under 3m from the "top" corner of the building envelope diagonally to the "lowest" one.
Our question now is whether an assignment to zone 4 at the minimum rate is justified, or how this classification can be objectively understood.
Do you have any tips on this? Another architect we worked with in the initial phase, for example, spoke of zone 3 and the mid-rate.
In addition, he estimates a flat rate for incidental costs of 8%.
Our building plot is a hillside plot (south slope). The slope runs diagonally within the building envelope with a height difference of just under 3m from the "top" corner of the building envelope diagonally to the "lowest" one.
Our question now is whether an assignment to zone 4 at the minimum rate is justified, or how this classification can be objectively understood.
Do you have any tips on this? Another architect we worked with in the initial phase, for example, spoke of zone 3 and the mid-rate.