Hi, I have granted such a power of attorney.
Thank you for your patience and your tips!
Best regards
Thorsten
--------- Status 17.03.15 -------
Substructure completed.
Panels laid.
String cables are in the house.
Voltage is accordingly present as well.
The house looks completely different now - I have to get used to it.
On the east side, panel salad (Thermo Solar + Photovoltaic). Somehow futuristic.
West side is spotless, only Photovoltaic, nicely symmetrically mounted, no TS in the way here.
All prerequisites are met for the electrical installation + inverter installation to start next Monday.
So far: good progress. A great installation team with 3 men - very diligent, competent, dedicated.