16.03.16: Start of photovoltaic assembly

  • Erstellt am 2016-03-16 10:51:22

toxicmolotof

2016-03-17 10:50:34
  • #1
Who is the network operator with you?
 

T21150

2016-03-17 10:51:39
  • #2
SW Velbert, behind it is indirectly - how could it be otherwise here: RWE.
 

toxicmolotof

2016-03-17 11:01:45
  • #3
But RWE is also Westnetz, and they do not participate in this mess either.

As long as the electrician has a license for the network, he can do it himself and is liable with his signature.

And even if he does not have a license for this network, but for another German network, he can apply for a "guest permit."

I really do not understand how one can behave so unfriendly to customers.
 

T21150

2016-03-17 11:06:27
  • #4
hm, thanks for the tip. I will be there on Monday when the electrician comes. I will talk to him. I can’t do more for now.
 

toxicmolotof

2016-03-17 14:04:25
  • #5
Exactly. See if and how there are ways to install the meter.

I would have to lie, but from the granting of power of attorney to our solar technician that he can order the meter from Westnetz until the start of the feed-in, 10 or 11 calendar days have passed.
 

T21150

2016-03-17 17:46:05
  • #6
Hi, I have granted such a power of attorney.

Thank you for your patience and your tips!

Best regards
Thorsten

--------- Status 17.03.15 -------
Substructure completed.
Panels laid.
String cables are in the house.
Voltage is accordingly present as well.
The house looks completely different now - I have to get used to it.
On the east side, panel salad (Thermo Solar + Photovoltaic). Somehow futuristic.
West side is spotless, only Photovoltaic, nicely symmetrically mounted, no TS in the way here.

All prerequisites are met for the electrical installation + inverter installation to start next Monday.

So far: good progress. A great installation team with 3 men - very diligent, competent, dedicated.
 

Similar topics
20.11.2015Solar / Photovoltaic from an economic perspective53
24.05.2024Planning empty conduits for satellite system and photovoltaic system14
30.06.2020Preparation for future photovoltaic?39
09.01.2020Which empty conduit is suitable for photovoltaics13
10.11.2021Photovoltaic system: Costs, saving potential? - Experiences?240
28.07.2020Photovoltaics and heat pump - meter confusion and cost issue12
06.10.2021Photovoltaic system / heat pump, do you have 2 meters?55
21.01.2021Photovoltaic systems yield experiences?22
23.04.2023Is preparing for photovoltaics in new construction sensible?81
14.06.2021Separate meter and electricity tariff for air-to-water heat pump sensible?103
03.09.2022Photovoltaic system offer for our single-family house162
19.06.2022Assessment of Photovoltaic System Offer33
06.07.2022How do photovoltaic system providers search for a new construction?24
15.04.2023Photovoltaics at any cost - current situation and offers169
14.06.2023Heat pump and household electricity all through one meter25
25.09.2023The supplier has incorrect meter numbers in the system - what to do?42
30.07.2024Terraced end house from 1915, photovoltaic system?34
27.09.2024Offer for photovoltaic system including storage - Storage yes/no?44
02.10.2024Photovoltaic - Position on the roof and only one meter?10
28.09.2024Single-family house photovoltaic system with 30KW20

Oben